- Dubai building permit in short
- Who applies for a building permit in Dubai?
- How to get a building permit in Dubai: the path from design to completion
- 1. Design and drawings
- 2. One request in Dubai BPS, the Dubai Municipality building permit system
- 3. Foundation inspection
- 4. Construction and the roof stage
- 5. Completion inspection and certificate
- Dubai building permit requirements: what is submitted
- Building permit insurance policy in Dubai
- Building permit fees in Dubai and timelines
- Changing an approved building permit
- How the permit links to inspections and completion
- Planning your own project
- Frequently asked questions
- How do I get a building permit in Dubai?
- How long does a Dubai Municipality building permit take?
- Do I need a building permit for a villa extension in Dubai?
- What are the building permit fees in Dubai?
- What are the Dubai building permit requirements?
- Who can apply for a building permit in Dubai?
- Do I need a consultant for a villa annex or majlis?
- Can I change the design after the permit is approved?
- Is the building permit insurance policy required for an annex?
- Need help with design and permit?
- Official sources
A building permit in Dubai for a villa annex, majlis or extension is requested electronically, and it is the document every later inspection and the completion certificate refer back to. This guide explains the Dubai Municipality building permit step by step from the official documents: who applies, what is submitted, how the insurance policy fits in, how long each step is meant to take and what to do if the design changes.
Dubai building permit in short
- Permit requests go through Dubai BPS, Dubai Municipality's unified electronic window. They are submitted by licensed engineering offices and contractors, not on paper, and the owner gives consent and the information the request needs.
- DM describes the process as three fixed steps: the building permit, the structural audit inspection (which includes the foundations), and the completion inspection with service connection. Each step is meant to be completed within three working days at most.
- The contractor provides a building permit insurance policy from a licensed insurer as a condition of the permit, for the works listed in Executive Council Resolution 28 of 2022. Your engineer or contractor confirms in Dubai BPS how your project is classified.
- Design changes, a change of contractor or engineering office, and the completion certificate are all separate request types in the same system.
- Official fees are set by DM and shown when the request is made, so this guide does not quote any figure.
Who applies for a building permit in Dubai?
The building permit is for your plot and your building, but the application is prepared and submitted by licensed professionals. DM circular 3-10-2 explains that engineering consultancy offices, contractors and companies use the unified window and sign in with UAE Pass. Under Law 14 of 2025 on engineering consultancy and Law 7 of 2025 on contracting, these activities are practised only by licensed and registered firms.
DM's decision 275 of 2024 defines an engineering office as the firm the owner hires for design, for supervising the building works, or for both. In practice:
- Design and permit stage: a licensed engineering office prepares the architectural, structural and services drawings and submits the request.
- Execution stage: the licensed contractor you appoint builds to the approved drawings and, as the insurance resolution requires, provides the policy.
For small projects such as an annex or majlis, a supervising consultant is not mandatory during execution, but a consultant or engineering office may be involved at the design and permit stage. DM documents reflect this: decision 275 of 2024 says that for permits that do not require appointing an engineering office, the owner takes that office's place in the completion-certificate route used when the contractor does not agree to the request, and the periodic inspection circular 11-6-1 asks for a work-start report where there is no consultant. The permit request itself shows which parties your project needs. A professional contractor is a natural partner here, because the drawings, the permit and the build are then planned as one job; see our services.
How to get a building permit in Dubai: the path from design to completion
1. Design and drawings
The engineering office visits the site and prepares the drawing set. Circular 3-1-1 asks consultants to visit the site before design and, for a new building proposal, to submit a preliminary structural report on neighbouring buildings. The electrical drawings, including transformer details where relevant, are part of the first-step set (circular 3-10-1). For the design rules your drawings must respect, see our Dubai Building Code guide.
2. One request in Dubai BPS, the Dubai Municipality building permit system
Since 22 June 2022 the unified window receives all requests for the Dubai Municipality building permit and related services: a new building permit, completion certificate, additions and modifications, permit renewal, amendment of permit data, and change of contractor or consultant (circular 3-10-2). The relevant government entities review the request in parallel against their own requirements. You do not need to collect preliminary approvals from each entity first; their requirements are published on the DM website and the request goes straight to the unified window (circular 3-2-1).
3. Foundation inspection
The second DM step is the structural audit inspection, which includes the excavation shoring and the foundations (circular 3-10-1). The DM engineer inspects before the foundations are poured, and pouring waits for approval. The building marks (the plot setting-out marks) come with the permit and are confirmed at this audit, without a separate survey request (circular 11-2-1).
4. Construction and the roof stage
The same rule applies before a concrete roof slab is poured. A sandwich-panel roof has no pour, so that pre-pour slab inspection does not apply to it. See our sandwich-panel roof guide and the comparison of annex building systems.
5. Completion inspection and certificate
At the end the contractor requests the completion inspection with the engineering office's approval. DM checks that the works match the permit and approved drawings and that the requirements of the relevant entities are met, then issues the completion certificate to the owner after the fees are paid (decision 275 of 2024). Our guide to Dubai Municipality inspections and the completion certificate covers this stage in detail.

Dubai building permit requirements: what is submitted
DM documents describe the submission for a building permit in Dubai as all documents, drawings, data and fees in one unified request. For an annex or majlis that means the drawing set prepared by the engineering office, including the electrical drawings. The exact list shown in Dubai BPS depends on the project, so rely on your engineer's checklist rather than a generic one.
Building permit insurance policy in Dubai
Executive Council Resolution 28 of 2022 introduced the building permit insurance policy and replaced the cash guarantees previously collected. Administrative decision 350 of 2022 stopped collecting the older insurances set by decision 27 of 2001. The key points:
- The contractor submits a policy issued by a licensed insurance company as a condition for issuing the permit, and DM may refuse the request if the policy does not meet the requirements.
- It applies to the contractor appointed for constructing buildings, additions and modifications of 300 m² or more, demolition and excavation shoring, and other works DM specifies.
- It covers material loss and damage and third-party liability. For new buildings and additions it runs from the permit date until one year after the completion certificate.
- It cannot be cancelled or amended without DM's prior approval.
The resolution lists constructing buildings without an area threshold, while the 300 m² threshold applies to additions and modifications, so ask your engineer or contractor to confirm in Dubai BPS how your annex, majlis or extension is classified.


Building permit fees in Dubai and timelines
Official building permit fees in Dubai are set by Dubai Municipality and collected through Dubai BPS when the service is requested (circular 3-10-1), so we do not quote figures here. On timing, DM states that each of the three steps is to be completed within three working days at most. That is DM's processing target for a complete request; it does not include preparing the drawings, answering comments or building.
| Step | Who acts | DM target |
|---|---|---|
| Building permit | Engineering office submits; entities review in parallel | Up to 3 working days |
| Structural audit inspection (includes foundations) | Contractor requests; DM engineer inspects | Up to 3 working days |
| Completion inspection and services | Contractor requests; DM inspects | Up to 3 working days |

Changing an approved building permit
- Design changes: additions and modifications are a request type in Dubai BPS. Circular 3-7-1 allows internal modification drawings made during execution to be submitted together before the completion request, if they do not conflict with the building regulations. Main modifications must be licensed before execution.
- Change of engineering office or contractor: decision 275 of 2024 asks for the owner's declaration, a technical report on the stage reached and a licensed replacement of a class not lower than the building requires. A new permit is issued in the replacement's name after fees, the replacement starts only after it is issued, and a new contractor provides the insurance policy.
- Exceptions to planning limits: if the design needs to depart from a planning or building limit, a separate amendment-request route exists under System 10 of 2006. That system sets a fee formula and says no fees are charged on requests by UAE nationals for their own private homes; confirm current treatment with DM. Raise the question early with your engineer.
- Permit not used yet: circular 11-6-1 asks for an electronic notice with the reasons if works have not started within six months of the permit date, or if they stop for more than three months.
How the permit links to inspections and completion
The permit starts a chain. The site keeps an audit file with the approved drawings, the DM engineer inspects at the stages above, and the completion certificate closes the file. Circular 3-1-2 also asks teams doing excavation and foundation work to assess neighbouring buildings and choose methods that limit vibration. For on-site rules see our site safety guide, and for materials and contractor licensing the guide to approved materials and contractors.
If a building was already built without a permit, that is a different path: see how to license an existing annex and our guide to violations and fines. Some plots follow other authorities, such as free zones and private development zones; the competent authority issues the permit there, so confirm which one applies to your plot first. The insurance resolution itself states that it applies across the emirate, including those zones.

Planning your own project
Before you apply for a building permit in Dubai, start with a clear brief, a licensed engineering office and a contractor who builds from the approved drawings. Our contractor checklist helps you agree the scope, the cost guide explains what drives the budget, and if you receive MBRHE support see the MBRHE guide.
Frequently asked questions
How do I get a building permit in Dubai?
A licensed engineering office or contractor submits the request through Dubai BPS, DM's unified electronic window, and the relevant entities review it in parallel. As the owner you give your consent and the information the request needs.
How long does a Dubai Municipality building permit take?
DM defines three steps, each to be completed within three working days at most. Preparing the drawings and answering any comments are separate from that target.
Do I need a building permit for a villa extension in Dubai?
Additions and modifications to a building are building works and are a request type in the unified system, so a villa extension permit in Dubai is handled through Dubai BPS. Your engineer confirms what your extension needs.
What are the building permit fees in Dubai?
Official fees are set by Dubai Municipality and shown when you apply, so we do not quote figures.
What are the Dubai building permit requirements?
DM describes the submission as all documents, drawings, data and fees in one unified request, with the electrical drawings included. The exact list shown in Dubai BPS depends on the project, so rely on your engineer's checklist.
Who can apply for a building permit in Dubai?
Licensed engineering offices and contractors submit the request through Dubai BPS, signing in with UAE Pass. As the owner you give your consent and the information the request needs.
Do I need a consultant for a villa annex or majlis?
For small projects such as an annex or majlis, a supervising consultant is not mandatory during execution, but a consultant or engineering office may be involved at the design and permit stage. The request in Dubai BPS shows what applies to your permit.
Can I change the design after the permit is approved?
Yes, through an additions and modifications request. Internal changes can be submitted together before the completion request if they do not conflict with the regulations, while main changes must be licensed before they are built.
Is the building permit insurance policy required for an annex?
The resolution applies to constructing buildings, additions of 300 m² or more, demolition and shoring. Ask your engineer or contractor to confirm in Dubai BPS how your project is classified.
Need help with design and permit?
We are happy to look at your plot and idea and explain the permit path. Message us on WhatsApp, use the contact page, try the free cost calculator or browse our projects.
This article summarises official Dubai Municipality documents for owners. The official DM website and the current versions of the documents prevail.
Official sources
- Local Order No. (3) of 1999 on regulating building works in the Emirate of Dubai, and Local Order No. (6) of 2000 amending it
- Executive Council Resolution No. (28) of 2022 on the building works licence insurance policy in the Emirate of Dubai
- Administrative Decision No. (350) of 2022 stopping collection of the insurances imposed by Administrative Decision No. (27) of 2001 on building insurances
- Administrative Decision No. (275) of 2024 approving the procedures for changing engineering offices and contracting companies and issuing completion certificates
- System No. (10) of 2006 on requests to amend planning and building regulations in the Emirate of Dubai
- Law No. (14) of 2025 on regulating engineering consultancy activities and Law No. (7) of 2025 on regulating contracting activities in the Emirate of Dubai
- Circular 3-10-1 (2021): steps of building licensing and Circular 3-10-2 (2022): launching the unified window for building licensing
- Circular 3-2-1 (2021): preliminary approvals, Circular 3-3-2 (2022): the building licence insurance policy, Circular 3-7-1 (2021): approval of modification drawings, Circular 3-1-1 (2021): site survey and neighbouring buildings and Circular 3-1-2 (2022): avoiding damage to neighbouring buildings
- Circular 11-2-1 (2021): auditing the building marks and Circular 11-6-1 (2021): periodic inspection and auditing of building sites