- In short
- Why approved products and licensed professionals matter
- Dubai Municipality approved contractors: what the law now expects
- Dubai contractor classification: classes and height limits
- Engineering offices: design, permit and supervision
- How to check Dubai Municipality approved materials
- Soil test in Dubai: what the Dubai Building Code says about soil investigation
- Changing a contractor or engineering office, and the completion certificate
- How to check Dubai Municipality approved contractors: a simple path for owners
- Frequently asked questions
- What are Dubai Municipality approved materials?
- How do I check that a building product is approved?
- Who counts as a Dubai Municipality approved contractor?
- Where can I find approved block factories in Dubai?
- How do I check approved reinforcing steel in Dubai?
- Do I need a consultant for an annex or majlis?
- Can I change my contractor or engineering office after the permit is issued?
- Is a soil test required before building?
- Do these rules apply everywhere in Dubai?
- Official sources
- Talk to us
Choosing Dubai Municipality approved contractors and approved materials is the quiet foundation of every good annex or majlis. This guide explains, from the official Dubai Municipality (DM) documents, how product approval works for steel, blocks, ready-mix concrete and insulation, what contractors and engineering offices must hold, and how owners can check both simply and calmly.
In short
- Dubai law now requires contractors and engineering offices to hold a trade licence and be registered with DM, and Dubai Municipality approved contractors work only within their classification (Law No. 7 of 2025 and Law No. 14 of 2025).
- Dubai Municipality approved materials appear in DM's lists of certified products and registered factories (steel, concrete blocks, insulation and more). Your contractor can show you the matching certificate or list entry before delivery.
- DM circulars place responsibility for steel, blocks and ready-mix concrete on the project team, so asking for certificates is normal professional practice.
- Changing a contractor or engineering office part-way through, and getting a completion certificate, follow a defined DM procedure (Administrative Decision 275 of 2024).
- For soil testing, the Dubai Building Code sets out how the ground should be investigated and who should carry out the tests.
Why approved products and licensed professionals matter
A villa annex is a small building, but it carries the same structural loads, heat and humidity as any other. DM's system exists so that the steel in your slab, the blocks in your walls and the concrete in your foundations have been tested by a recognised laboratory, and so that the people designing and building have been checked as competent. For a villa owner that is good news: it gives you a clear, shared standard to work to with your contractor, from the first drawing to the completion certificate. The sections below cover Dubai Municipality approved contractors first, then approved products.

Dubai Municipality approved contractors: what the law now expects
Law No. (7) of 2025 regulates contracting activities in Dubai. It was published in the Official Gazette on 15 July 2025 and took effect six months after publication. Its main points for an owner choosing among Dubai Municipality approved contractors are simple:
- A contractor must hold a valid trade licence and be registered in DM's contractor register. The law also prohibits individuals and entities from contracting with a firm that lacks the licence and registration.
- Each contractor is classified and works only within its activity and class. A first-time contractor starts at the lowest class.
- Technical staff must hold a professional competency certificate.
- Registration lasts one year and is renewable, so ask for the current certificate rather than an old one.
- A contractor carries out the contracted work with its own technical staff. Passing some works to another contractor is allowed only under the law's conditions: the other contractor must be licensed and registered, and DM approval is required.

The law applies to contractors across the emirate, including special development zones and free zones. Permit procedures in some areas, such as free zones or master-developer communities, follow other authorities, so confirm which authority issues your permit.
Dubai contractor classification: classes and height limits
Under Dubai's contractor classification, Administrative Decision 253 of 2021 links a contractor's class to the building height it may handle and the number of core engineers it must employ:
| Class | Building height | Core engineers required |
|---|---|---|
| First | Unlimited floors | 3 |
| Second | Up to ground + 12 | 2 |
| Third | Up to ground + 4 | 1 |
| Fourth | Up to ground + 1 | 1 |
A villa annex normally sits in the lowest height band, but when comparing Dubai Municipality approved contractors, what counts is the class shown on each contractor's registration. The decision also requires engineers to be members of the Emirates Engineers Association and to pass DM's technical competency tests. Law 7 of 2025 asks DM to keep its classification system updated, so check the current system on the DM website.
Engineering offices: design, permit and supervision
Law No. (14) of 2025 regulates engineering consultancy activities. It was published in the Gazette on 7 October 2025, took effect six months later, and replaces Local Order 89 of 1994. Under it, an engineering office needs a trade licence and registration, employs registered engineers with a professional competency certificate, and has a registered engineer as its manager. It also keeps a professional separation: an engineering office cannot be an owner, partner, manager or employee of a contracting firm or a building-materials trading firm, which keeps its advice independent of the contractor.
In small projects such as an annex or a majlis, a supervising consultant is not required during execution, but a consultant or engineering office may take part at the design and permit stage. DM's own procedures recognise this: Administrative Decision 275 of 2024 notes that for building permits which do not require appointing an engineering office, the owner takes the office's place in the change and completion procedures. Where an office is appointed, DM Circular 13-5-1 of 2023 asks for a written consultancy contract with the licensed office before design and supervision work, and Law 14 of 2025 requires the office to supervise continuously the works it is contracted for. See our building permit guide for the permit stage.


How to check Dubai Municipality approved materials
Dubai Municipality approved materials are certified by DM's Dubai Central Laboratory Department through a factory assessment scheme, and the department also keeps registers of suppliers. On the DM "certified products" page you will find downloadable lists: products certified under the factory assessment scheme, steel importer registration, products certified under Type 1, and registered block factories under Type 2. The page does not give a step-by-step process, so the practical method is to open the list that matches the product and find the manufacturer and certificate number. The lists are updated from time to time, so always use the current download.
| Product | What DM circulars and lists say | What to ask your contractor for |
|---|---|---|
| Reinforcing steel | Circular 7-1-1 of 2021: steel must come from manufacturers or importers registered on the DM site and carry Dubai Central Laboratory conformity marks. The supervising consultant and the contractor are responsible. | Supplier name, registration and conformity certificate for each delivery. |
| Concrete blocks | Circular 7-3-1 of 2021: conformity certificates from Dubai Central Laboratory must be obtained before blocks are used on site. DM also lists registered block factories, so approved block factories in Dubai can be confirmed by name. | The block factory name and its certificate or list entry. |
| Ready-mix concrete | Circular 7-2-1 of 2021: plants and site mixing units must be registered with DM; concrete quality is a shared responsibility of consultant, contractor and plant. | The name of a registered ready-mix plant and delivery notes. |
| Thermal insulation | DM publishes a list of certified insulation manufacturers with certificate numbers and standards (for example polystyrene, polyurethane and mineral wool). | Manufacturer, product type and certificate number, matching the approved drawings. |
For concrete mixes, DM Circular 7-2-2 of 2026 temporarily relaxes certain cement-replacement requirements for superstructure concrete only. Foundation concrete is unchanged, and the Dubai Building Code minimum for structural concrete is 35 MPa (grade C28/35). Insulation choices are covered in our Al Sa'fat green buildings guide, and wall and roof systems are compared in block, sandwich panel or cement board.
Soil test in Dubai: what the Dubai Building Code says about soil investigation
Part K of the Dubai Building Code (residential villas) describes how ground investigation, including the soil test, should be done. The key points are practical:
- Soil investigation follows recognised standards (BS 5930 and BS EN 1997-2).
- The scope depends on the building position, loads, number of floors and shape, and on site conditions such as geology and drainage.
- For an individual villa, at least two boreholes per villa; for attached villas in a community, one per plot.
- Borehole depth extends to at least three times the shortest dimension of the proposed foundation.
- Tests are carried out in laboratories licensed and accredited by the Emirates International Accreditation Centre (EIAC).
- The laboratory issues a factual report, and the engineer reviews and approves an interpretive report that recommends the foundation system and allowable bearing capacity.

Part K is written for residential villas, so ask your design engineer how it applies to your annex or majlis and what scope of testing they recommend. See the Dubai Building Code guide for the wider code.
Changing a contractor or engineering office, and the completion certificate
Administrative Decision 275 of 2024 gives a clear route so that the work and the permit stay in order. In summary:
- The owner submits the request with a declaration, and the outgoing office or contractor provides a technical report on the stage reached and its match to the permit and drawings. The incoming party confirms the report.
- The incoming office or contractor must be licensed and its class must not be lower than the building's class.
- DM issues a new building permit in the new party's name after fees, and the new party cannot start before it. A new contractor also provides the insurance policy required by Executive Council Resolution 28 of 2022.
- If the outgoing party does not consent, DM asks for its reply within five working days and sets a handover period of up to 15 days for an engineering office and up to 30 days for a contractor.
- For the completion certificate, DM inspects to verify the works follow the permit and drawings and other authorities' requirements, then issues the certificate to the owner after fees. The owner may submit these requests.
Inspections themselves are covered in our inspection and completion certificate guide. As you may know from site, the DM engineer inspects before foundations are poured and pouring waits for approval, and the same applies before a concrete roof slab; a sandwich-panel roof has no pour, so that slab step does not apply to it.
How to check Dubai Municipality approved contractors: a simple path for owners
DM also publishes model contracts for villa projects (a building contract and a consultancy contract) and lists the clauses a contract should include: parties, scope, order of documents, responsibilities, value, payment schedule, duration, handling of changes, delay consequences, termination, document ownership, notices and dispute resolution. Our 12-point contractor checklist walks through the same ideas in plain language.

Frequently asked questions
What are Dubai Municipality approved materials?
They are products that have a DM conformity certificate or whose manufacturer or importer is registered with the Dubai Central Laboratory. DM lists certified products, steel importers and registered block factories on its certified products page.
How do I check that a building product is approved?
Open the matching list on the DM certified products page and look for the manufacturer and certificate number. Your contractor can provide the certificate and the supplier's details for steel, blocks, ready-mix concrete and insulation.
Who counts as a Dubai Municipality approved contractor?
A Dubai Municipality approved contractor holds a valid trade licence, is registered in DM's contractor register under Law 7 of 2025 and works within its classification. Ask to see the current registration certificate.
Where can I find approved block factories in Dubai?
The DM certified products page includes a downloadable list of registered block factories. Look for the factory name and its certificate or list entry, and ask your contractor to confirm it before blocks are used on site, since Circular 7-3-1 of 2021 asks for Dubai Central Laboratory conformity certificates before use.
How do I check approved reinforcing steel in Dubai?
Circular 7-1-1 of 2021 asks that steel comes from manufacturers or importers registered on the DM site and carries Dubai Central Laboratory conformity marks. Ask your contractor for the supplier name, registration and conformity certificate for each delivery.
Do I need a consultant for an annex or majlis?
In small projects such as an annex or a majlis, a supervising consultant is not required during execution, but a consultant or engineering office may take part at the design and permit stage. Check with DM what your permit type requires.
Can I change my contractor or engineering office after the permit is issued?
Yes, through the procedure in Administrative Decision 275 of 2024: a request, a technical report on the stage reached, a licensed replacement of an adequate class, and a new permit in the replacement's name.
Is a soil test required before building?
The Dubai Building Code describes soil investigation for villas, with at least two boreholes per villa and tests in EIAC-accredited laboratories. Your design engineer will confirm what applies to your plot and structure.
Do these rules apply everywhere in Dubai?
DM's rules cover the DM jurisdiction. Some areas, such as free zones or master-developer communities, follow other authorities for permits, so confirm yours first.
Official sources
- Law No. (7) of 2025 regulating the practice of contracting activities in the Emirate of Dubai
- Law No. (14) of 2025 regulating the practice of engineering consultancy activities in the Emirate of Dubai
- Administrative Decision No. (275) of 2024 approving procedures for changing engineering offices and contractors and issuing completion certificates
- Administrative Decision No. (253) of 2021 approving technical requirements and criteria for qualifying engineers working in the building sector in Dubai
- Circular No. (7-1-1) of 2021 on steel products used for concrete reinforcement, Circular No. (7-2-1) of 2021 on concrete, Circular No. (7-2-2) of 2026 on temporary application of supplementary cementitious materials and Circular No. (7-3-1) of 2021 on concrete blocks
- Administrative Decision No. (316) of 2012 on control of ready-mix concrete plants and on-site mixing units in Dubai
- Circular No. (13-5-1) of 2023 on guidance contracts for engineering consultancy and building contracting for villa projects and Circular No. (13-4-1) of 2021 on subcontractors
- Dubai Municipality certified products lists (Dubai Central Laboratory)
- Dubai Building Code, Part K: Residential Villas (Decree No. 45 of 2021)
This article summarises official Dubai Municipality documents for owners. It is not legal advice, and the official DM website and the current versions of the documents prevail.
Talk to us