10 min read
In this article
- Shams Dubai solar for villas in short
- What is Shams Dubai and who is it for?
- Who can install solar panels for a villa in Dubai?
- Shams Dubai connection process: the stages
- 1. Appoint an enrolled consultant or contractor
- 2. Application and design approval
- 3. Inspection
- 4. Agreement, meters and connection
- 5. Generation and net metering
- How long does the Shams Dubai connection take?
- How much does the DEWA connection cost for solar?
- How big can a villa solar system be?
- Do I need a Dubai Municipality permit for rooftop solar?
- Net metering in a Dubai villa: do I get paid for exported electricity?
- Adding solar when you plan an annex or extension
- Home EV charger on the same villa supply
- Frequently asked questions
- Can any company install solar panels for my villa?
- How much does the DEWA connection cost for solar?
- How big can my solar system be?
- Do I get paid for exported electricity?
- Do I need a permit from Dubai Municipality for rooftop solar?
- How long does Shams Dubai take?
- Can I apply to DEWA myself as the owner?
- Can I charge an electric car at home with solar?
- Need help planning solar with your annex or extension?
- Official sources
Shams Dubai solar for a villa lets you generate electricity on your own roof, use it in the house and export the surplus to DEWA's grid, and the connection runs through a DEWA-enrolled solar consultant or contractor. This guide takes villa owners, including those planning an annex, majlis or extension, through the official Shams Dubai steps: who does what, the times and the connection fee DEWA states, the capacity limit, the Dubai Municipality permit and net metering.
Shams Dubai solar for villas in short
- Shams Dubai is DEWA's initiative for household and building owners who install solar panels and connect them to the grid. The power is used on site and the surplus is exported.
- Only an enrolled solar consultant or contractor can apply. The owner does not apply directly, and without an enrolled installer there is no grid connection and no net metering.
- DEWA states 12 working days for design approval and the estimate, 1 working day for inspection and 1 working day for metering. A plant above 100 kW also has a performance test.
- The application is free. The one-off connection fee is currently AED 1,500 per generator, and DEWA installs the smart meter at normal service charges.
- System size is capped by a share of your total connected load, and DEWA may set a lower limit for the grid.
- Surplus energy is credited against future consumption. The credit does not transfer to a new owner or tenant.
What is Shams Dubai and who is it for?
Shams Dubai lets household and building owners install photovoltaic (PV) panels and connect them to DEWA's network. The electricity you generate supplies your own villa first, and anything you do not use is exported to the grid. DEWA states that the initiative implements Executive Council Resolution 46 of 2014. For a villa owner that usually means rooftop panels on the main house, or on a new annex, majlis or service block once its roof is built.
It is a connection and metering arrangement, not a product. DEWA sets the rules for how a system joins the network, and a licensed professional designs and installs the system itself. DEWA also offers an online Shams Dubai calculator that you can try before you speak to anyone.
Who can install solar panels for a villa in Dubai?
Only a DEWA-enrolled solar consultant or contractor can take your project to the grid. DEWA says plainly that if the installer is not enrolled there is no grid connection and no net metering, so this is the first thing to check before you sign anything. Our guide to agreeing scope with a contractor and the note on approved contractors and materials help you ask the right questions. The "Getting Solar Permits and Connections" service is offered to enrolled solar consultants and contractors.
| Party | What they do |
|---|---|
| Owner | Appoints an enrolled installer, signs the connection agreement and holds the operation and maintenance contract |
| Solar consultant or contractor | Designs the system, submits the DEWA application, installs and tells DEWA when the site is ready for inspection |
| DEWA | Approves the design, issues the estimate, inspects, installs the meters and connects |
| Dubai Municipality | Issues the building permit for the civil or structural part and the completion certificate |
Shams Dubai connection process: the stages
1. Appoint an enrolled consultant or contractor
Share your roof plan, your recent bills if you have them and what you want the system to do. The installer sizes the system against your connected load and the limit described below.
2. Application and design approval
The installer submits the application on your behalf. DEWA approves the design and issues the connection fee estimate. This is the stage where a clear electrical design pays off, which is why solar belongs in the conversation when you plan a new annex or extension rather than after it is finished.
3. Inspection
When the installation is ready, the consultant or contractor notifies DEWA and DEWA inspects the site. Above 100 kW, DEWA also requires a plant performance test.
4. Agreement, meters and connection
After the inspection the connection agreement is signed, DEWA installs the meters and the system is connected.
5. Generation and net metering
Your system generates, you use what you need and the surplus is exported. DEWA offsets your bill with the exported energy, as explained under net metering below.

How long does the Shams Dubai connection take?
These are the service times DEWA publishes for the solar application. They count DEWA's own work, not the time to prepare drawings, answer comments or build.
| Stage | Who acts | DEWA time |
|---|---|---|
| Design approval and estimate | Installer applies; DEWA reviews | 12 working days |
| Inspection | Installer requests; DEWA inspects | 1 working day |
| Performance test | Plants above 100 kW only | 3 working days |
| Metering | DEWA installs the meters | 1 working day |
How much does the DEWA connection cost for solar?
DEWA states that the application itself is free. The official charges it names are:
| Item | DEWA statement |
|---|---|
| Application | Free of charge |
| Connection fee | Currently AED 1,500 per renewable generator, one-off, mainly for the generation check meter |
| Smart meter | Bi-directional meter installed at normal service charges, with no extra cost |
| Estimate | Issued by DEWA after design approval |
DEWA words the connection fee as "currently", and it applies the figure when the application is made, so confirm it with your installer at that point. These are authority fees only. The panels, inverter, installation and the operation and maintenance contract are agreed separately with your installer, and this guide does not quote prices for them.
How big can a villa solar system be?
DEWA's connection process says the installed capacity cannot exceed the applicable share of your total connected load, as set out in section 2.2 of the Shams Dubai Connection Conditions. DEWA may also set a lower limit where the grid requires it. The numeric share is in DEWA's conditions document and we do not restate it here, so ask your installer to confirm the exact figure for your villa.
This matters when you extend. Your total connected load is part of the electrical design, so a plan that adds an annex or majlis may change the load the system is measured against. Our guide to increasing the electrical load for a villa extension explains that side, and the guide to the DEWA electricity connection for a villa annex covers the supply itself.
Do I need a Dubai Municipality permit for rooftop solar?
DEWA's builder FAQ says a building permit from Dubai Municipality is needed for the civil or structural part of the installation, with a completion certificate afterwards. For free-zone plots the competent authority applies instead. Your installer or engineering office confirms what your system needs. Our guide to the Dubai building permit for an annex, majlis or extension shows how the permit process works, and the completion certificate guide covers the closing stage.
Separately, DEWA requires an operation and maintenance contract with an enrolled provider. Ask for it to be part of the offer from the start.

Net metering in a Dubai villa: do I get paid for exported electricity?
Under DEWA net metering, surplus electricity your system exports is credited and offsets your future consumption. DEWA describes the exported energy as a credit that offsets your bill, so plan the system around reducing what you draw from the grid. The credit is tied to the account: DEWA states it does not transfer to a new owner or tenant. If you sell or rent the villa, do not count on the credit moving with the property.
Adding solar when you plan an annex or extension
If the villa is already being extended, one design meeting can cover both. Points worth agreeing with your engineer and installer, as practical planning rather than DEWA rules:
- Roof area and structure: which roof carries the panels, and whether the roof type and structure suit them. See our sandwich panel roof guide and the comparison of annex building systems.
- Electrical room and distribution board: where the inverter, protection and meters sit, and that there is space for them.
- Cable route: a clear, protected route from the roof to the board that is decided before finishes go on.
- Total connected load: the figure on which the capacity limit is measured, taken from the final electrical design.
- Heat and insulation: roof build-up and thermal layers, covered in our Al Sa’fat and insulation guide.
Agreeing a few things early keeps the project smooth: an enrolled installer, drawings that match the final load and the roof details. A single contractor who builds the annex and coordinates the electrical works makes this simpler, and you can see how we work on our villa construction page. Owners of larger projects can read about building construction in Dubai.

Home EV charger on the same villa supply
If you also plan to charge an electric car at home, DEWA's consumer FAQ says a home charger can be installed by a third party behind your meter, like other home appliances. DEWA advises using DEWA-approved electrical contractors, and home charging is billed on your normal DEWA bill at standard residential rates. DEWA's text does not say how a charger affects your villa's supply, so ask your electrical engineer to include it in the load assessment, particularly when solar is planned too. For the supply side, see our guide to increasing the electrical load for a villa extension.
Frequently asked questions
Can any company install solar panels for my villa?
No. Only a DEWA-enrolled solar consultant or contractor can take the project to grid connection and net metering. Check the enrolment before you agree to a quote.
How much does the DEWA connection cost for solar?
The application is free. DEWA states a one-off connection fee, currently AED 1,500 per generator, and the smart meter at normal service charges. DEWA applies the figure when the application is made.
How big can my solar system be?
Capacity cannot exceed the applicable share of your total connected load under DEWA's Shams Dubai Connection Conditions, and DEWA may set a lower limit for grid reasons. Your installer confirms the figure for your villa.
Do I get paid for exported electricity?
DEWA credits the surplus against your future consumption through net metering. That credit does not transfer to a new owner or tenant.
Do I need a permit from Dubai Municipality for rooftop solar?
DEWA says a Dubai Municipality building permit is needed for the civil or structural part of the installation, with a completion certificate afterwards. Your installer confirms what applies to your roof.
How long does Shams Dubai take?
DEWA states 12 working days for design approval and the estimate, 1 working day for inspection and 1 for metering. Plants above 100 kW also have a performance test. Preparing drawings and installing are extra.
Can I apply to DEWA myself as the owner?
No. DEWA's solar application is submitted by an enrolled consultant or contractor, and you sign the connection agreement later in the process.
Can I charge an electric car at home with solar?
A home charger sits behind your meter, installed by a DEWA-approved electrical contractor and billed at residential rates. Ask your engineer to check the villa's load with solar and the charger together.
Need help planning solar with your annex or extension?
We are happy to look at your villa and explain how the electrical design and the roof fit together. Message us on WhatsApp, use the contact page, try the free cost calculator or browse our projects.
This article summarises official DEWA pages for owners and is not legal or engineering advice. The official DEWA website and the current Shams Dubai Connection Conditions prevail.
Official sources
- DEWA: Shams Dubai
- DEWA: Shams Dubai connection process
- DEWA: Getting Solar Permits and Connections
- DEWA: Consumer FAQs
- DEWA: Builder FAQs
- DEWA: Shams Dubai solar calculator