Low-rise and mid-rise buildings in Dubai: G+1 to G+12 explained

Low rise building construction in Dubai covers everything from a G+1 up to a G+12, and the rules change in steps as the building grows: how the height is counted, which contractor class may build it, and how much the lifts, fire design, structure and foundations ask of the design. This guide explains how Dubai counts floors, what changes between low-rise and mid-rise buildings, and what to weigh when choosing between G+4, G+6 and G+12 for an investment plot, from the official Dubai Municipality (DM) documents.

In short

  • DM writes height as "ground + N floors". G+12 is a ground floor plus twelve floors above it, and a basement or mezzanine follows its own counting rule.
  • There are two yardsticks. The Dubai Building Code groups buildings by height in metres (low-rise up to 15 m, mid-rise more than 15 m and less than 23 m, high-rise 23 m up to 90 m), while DM's contractor classes are set by floors: ground + 1, ground + 4, ground + 12 and unlimited.
  • Taller buildings ask more of the same path: lifts under Part D, fire and life-safety design under the UAE Fire and Life Safety Code, central gas, Al Sa'fat Silver level, accessibility, and a licensed structural engineer with DM foundation checks.
  • The permit route is the same for every height: Dubai BPS, three DM steps and DM inspections at the foundation, structure and completion stages.
  • This guide quotes no prices or fees. DM shows its fees when you apply, and your plot's own rules decide how many floors you may build.
Flat illustration of a G+12 residential building with podium parking levels and a regular facade grid
Illustration: a G+12 residential building, a ground floor plus twelve floors.

How does Dubai count floors? Ground floor, mezzanine, podium, basement and roof

The Dubai Building Code (Decree 45 of 2021) defines the terms that decide the count, and DM's decisions use the long wording, such as "ground + 12 floors". Write your brief the same way.

TermHow the Code treats it
Ground floor (G)The first floor of the building above the reference level, the plot's access level at the boundary.
FloorThe part of a building between the top surface of one floor and the top surface of the floor above.
BasementA floor wholly or partly below the reference level that is not the first floor above it. Its roof slab underside may not rise more than 1,200 mm above that level.
Mezzanine (M)An intermediate level of one third of the floor it sits in, or less. A larger partial floor counts as a floor.
PodiumThe group of the lowest floors of a tower, which may include the ground floor and has planning requirements different from the repeated tower floors.
RoofFor villas, Part K treats built area on the roof above 50% of the slab, or not set back 1.5 m from the edges, as an ordinary floor.

So a drawing may show G+M+4 and still be a ground plus four building, as long as the mezzanine stays within one third of its floor. A larger one makes it a G+5. Ask your engineer to state in writing the number of floors, the height in metres and how lift rooms, stair rooms and rooftop services are treated on your plot.

Flat illustration of three low-rise buildings of G+2, G+4 and G+6 side by side with dashed lines marking each floor level
Illustration: G+2, G+4 and G+6 side by side, with dashed lines at each floor level.

What is a low-rise and a mid-rise building in Dubai?

The Code sorts buildings by height in metres, measured as the UAE Fire and Life Safety Code (UAE FLSC) defines it:

Dubai Building Code, Part B definitions: a low-rise building is up to 15 m high and a mid-rise building is more than 15 m and less than 23 m, both measured as the UAE Fire and Life Safety Code defines
Excerpt from the Dubai Building Code (Arabic 2021 edition), Part B definitions of low-rise and mid-rise buildings (Arabic original), Dubai Municipality. In short: a low-rise building is up to 15 m high and a mid-rise building is more than 15 m and less than 23 m, both measured as the UAE FLSC defines. official page
BandHeight
Low-riseUp to 15 m
Mid-riseMore than 15 m and less than 23 m
High-rise23 m or more, up to 90 m
Super high-riseAbove 90 m

The Code does not convert floors into metres, because floor-to-floor height is a design choice. That is why "G+12" tells you the floor count and the contractor class, but not the band: the band follows the metre height of your design, which your engineer states. Authorities also check height against the plot's development control regulations (DCR) or site plan and, near airports, Dubai Civil Aviation Authority limits. Our G+4 and G+6 residential building guide goes deeper on the lower end of this range, and villas of up to three floors have their own part of the Code.

What changes as a building gets taller, from G+1 to G+12?

Lifts

Part D of the Code covers lifts, escalators and moving walks, and sets the minimum number of passenger lifts from the estimated number of occupants and the number of entrance floors. Decision 225 of 2024 exempts only buildings on land of 250 m² or less that are ground + 2 floors or less and have 100 occupants or fewer, both together. Above G+2, plan the lift core from the start and ask for the lift calculation.

Fire and life safety

The Code refers to the UAE FLSC, and where the two differ the more stringent applies. Circular 5-1-1 bars combustible materials and materials that weaken fire resistance, thermal insulation and its fixings included, unless Dubai Civil Defence has approved them under the latest UAE FLSC. For multi-storey buildings, circular 6-1-1 asks for central gas distribution, with the network design submitted with the licence drawings and Civil Defence-approved materials and controls. This guide quotes no fire-system thresholds by height; your engineer confirms what applies.

Parking

The Code's Table B.13 gives residential ratios by unit size: one space for a studio, one-bedroom or two-bedroom unit, two for three or four bedrooms, and three for five bedrooms, a duplex or a penthouse. Ratios in the plot's site plan or DCR take priority. Buildings with more than 20 spaces also provide preferred spaces for hybrid and electric vehicles. More floors mean more units to serve, and whether the spaces sit at ground level, in a podium or in a basement is a design decision within the plot's rules.

Structure, soil and foundations

Under decision 37 of 2021, the structural design of buildings is done by a qualified structural engineer licensed in Dubai and approved by the competent department. Before the foundation pour, the contractor attaches the foundation level, soil bearing capacity and design assumptions to the DM request, and confirms the foundation level against the soil investigation report before the blinding concrete; piles are tested by an independent DM-licensed laboratory (circular 11-4-1). The Code’s soil investigation figures sit in its villa part, so for a G+4 to G+12 building your structural engineer scopes the investigation and states what it covers.

Green building and accessibility

Al Sa'fat Silver level is mandatory for all building types, and DM issues the certificate with the completion certificate. Circular 11-8-1 of July 2025 makes compliance with the Code's accessibility requirements a condition of the completion certificate. Our Al Sa’fat and insulation guide has the details.

Which contractor can build a G+12? Classes by building height

Under Law 7 of 2025, nobody may work as a contractor without a trade licence and registration in DM's register, a contractor works within its class, and owners may not contract an unregistered firm. In DM's Table 4 of decision 253 of 2021, each class is tied to a building height and to the core engineers it must employ, so the class reflects registered engineering capacity.

Your buildingLowest class whose limit covers it
G+1Class 4 (ground + 1 floor)
G+2 to G+4Class 3 (ground + 4 floors)
G+5 to G+12Class 2 (ground + 12 floors)
Above G+12Class 1 (unlimited floors)

Higher classes also cover lower heights. Law 7 of 2025 asks DM to update its classification system, so ask any contractor, including us, for its current DM registration and class. Our approved materials and contractors guide shows how to check, and the 12-point contractor checklist lists what to put in the agreement.

The engineering office's role

DM documents assume a licensed engineering office is part of a new building project. Decision 275 of 2024 defines it as the firm the owner hires for design, supervision or both, and Law 14 of 2025 reserves the activity for licensed, registered offices. The contractor follows the contract and the instructions of the office the owner appoints, and requests the completion certificate with that office's approval. An office registrant may not be an owner, partner or employee of a contractor, so design and execution have separate, clearly defined roles. Agree in writing whether your office provides design alone or design and supervision.

Permit and inspection path for a low-rise or mid-rise building

Path from plot rules to completion for a low-rise or mid-rise buildingFive stages: plot rules and height, contractor class and engineering office, permit request in Dubai BPS, foundation and structure checks, completion inspection and certificate.1Plot rules and heightDCR or site plan sets the floors2Class and engineering officecontractor class covers the height3Permit request in Dubai BPSone request, entities review in parallel4Foundation and structure checksDM engineer approves before pouring5Completion inspectionservices connected, certificate issued
The general path. Steps 3, 4 and 5 follow DM's three fixed steps; the pre-pour slab check applies only to a concrete roof slab.

The route is the same from G+1 to G+12, and it is explained step by step in our building permit guide. Licensed offices and contractors submit one request in Dubai BPS with UAE Pass, and the relevant entities review it in parallel without separate preliminary approvals. DM sets three steps, the permit, the structural audit including foundations, and the completion inspection with service connection, each to be completed within three working days at most. The contractor provides the building permit insurance policy as a condition of the permit; Resolution 28 of 2022 lists constructing buildings, and the policy runs to one year after the completion certificate.

DM limits inspections of buildings under construction to the high-risk stages: foundation pouring, structure and completion (circular 13-3-1). The DM engineer inspects before the foundations are poured and before a concrete roof slab is poured, and pouring waits for approval. After the completion inspection DM issues the certificate to the owner, and Local Order 3 of 1999 bars occupation before it. Our guide to DM inspections and the completion certificate covers the last stage, and the Dubai Building Code guide explains the design rules.

G+4, G+6 or G+12 for an investment plot: what to weigh

FactorWhat to weigh
Plot rulesThe DCR or site plan sets permitted use, floors, coverage, setbacks and parking, so it sets the ceiling. Get it in writing before comparing options.
Contractor classA G+4 sits at the limit of class 3. A G+6 and a G+12 need class 2 or class 1.
Height bandAsk for the metre height and the band in writing, because the Code and the fire code work in metres.
Lifts and coreAll three are outside the lift exemption. The number of lifts follows occupants and entrance floors.
ParkingTable B.13 follows the unit mix, and the plot's own ratios take priority. Decide early where the spaces go.
FoundationsLoads grow with height, and the engineer sets the soil investigation and foundation design. DM checks the same stages.
Use mixShops on the ground floor make a mixed-use building, a separately defined use. Confirm the permitted use first.

Our low-rise building cost guide explains how to compare offers on the same drawings and bill of quantities (BOQ), without quoting any figure here.

Related services

For a residential building, see our building construction company in Dubai page, which explains how we work with the registered consultant and the owner, and our villa construction page for single-family homes.

Frequently asked questions

How does Dubai count floors, and is the ground floor included in G+1?

The ground floor is the first floor above the reference level, and G+1 adds one floor above it, two in total. A basement is counted separately.

What is the difference between low-rise and mid-rise buildings in Dubai?

In the Dubai Building Code, low-rise means up to 15 m and mid-rise means more than 15 m and less than 23 m, measured as the UAE FLSC defines height.

How many floors is a G+12 building?

A ground floor plus twelve floors above it. A basement or a mezzanine of one third of a floor or less is counted under its own rule.

Which contractor class can build a G+12 building in Dubai?

In DM's Table 4, class 2 covers up to ground + 12 floors and class 1 has no floor limit. Confirm the current class on DM's register.

Do I need a lift in a G+4 or G+12 building?

The exemption in decision 225 of 2024 covers only ground + 2 floors or less with 100 occupants or fewer on land of 250 m² or less, so both follow Part D of the Code.

Does a G+12 building need a different permit path from a G+4?

No. The request goes through Dubai BPS in the same three steps, and DM inspects the same high-risk stages. The design, the engineers and the contractor class are what change.

Need help with a low-rise or mid-rise building?

We are happy to look at your plot and plan and explain the route. Message us on WhatsApp, use the contact page, read about our building construction service, or browse our projects. If you are planning a single house instead, see our villa construction service.

This article summarises official Dubai Municipality documents for owners and is not legal advice. The official DM website and the current versions of the documents prevail.