Annex BOQ Quantity Estimate (Concrete, Steel, Blocks)

Use this annex BOQ quantity estimate to answer the first question every owner asks: how much material does my annex need? Enter the annex length and width, the number of floors, the floor height, the slab thickness, the rooms, the windows and the doors, and get the order quantities: ready-mix concrete in m³ and trucks, reinforcing steel in tonnes, blocks (طابوق), cement bags and sand for the block mortar and plaster, tiles in m² and paint in litres. It is a quick BOQ-style estimate of quantities only, in metric units, for villa annexes, majlis extensions and small buildings in Dubai and the UAE. Pick one of the three site examples to see how it works.

How the annex quantities are calculated

The annex is treated as a rectangle of length L and width W on a regular column grid. Every figure below is a planning rule stated here, so you can check it against your drawings. Nothing comes from a code or from an authority unless said so.

Concrete

  • Column lines: nx = ceil(L ÷ spacing) + 1 along the length and ny = ceil(W ÷ spacing) + 1 along the width. Columns = nx × ny.
  • Pad footings: 1.2 × 1.2 × 0.5 m for a ground floor annex, 1.6 × 1.6 × 0.6 m for ground + first floor, each on 100 mm blinding that is 0.2 m wider.
  • Columns: 300 × 300 mm, with a height of floors × floor height + 1.0 m below the ground slab.
  • Beams: the beam run is nx × W + ny × L (every column line, edges included). Ground beams are 300 × 500 mm. Floor beams are 250 mm wide and 500 mm deep overall, so the part under the slab is 500 − slab thickness (the part inside the slab is not counted twice), one level per floor.
  • Slabs: floors × L × W × thickness. The optional ground slab on grade is L × W × 150 mm.
  • Order quantity = net volume × (1 + waste), 5 percent by default. Trucks = order ÷ truck size, rounded up.

Steel

Steel is the concrete volume of each element × a planning ratio in kg/m³: pads 70, columns 180, ground beams 110, floor beams 140, slabs 100, ground slab 35. The steel level option multiplies them by 0.85 (light) or 1.2 (heavy). These are rule-of-thumb values used for early estimates, not values from a code, and they vary between engineers: the bar schedule from the structural drawings governs. For a detailed weight use the rebar calculator or the slab calculator.

Blocks, mortar and plaster

  • External walls: perimeter × (floor height − 0.5 m beam) × floors, plus a 1.0 m roof parapet if ticked, minus windows (1.5 × 1.2 m) and external doors (1.0 × 2.1 m). They are 200 mm hollow blocks.
  • Partitions: length per floor × (floor height − slab thickness) × floors, minus internal doors (1.0 × 2.1 m). They are 100 mm blocks. If you do not enter the length, it is estimated as (rooms − 1) × (L + W) ÷ 3, a rule of thumb for rooms laid out on a grid. Enter the length measured on the plan for a better result.
  • Blocks: 400 × 200 mm with a 10 mm joint is 1 ÷ (0.41 × 0.21) = 11.61 per m², plus the waste allowance. The mortar uses the same method as the block calculator: hollow blocks, mortar 1 : 4, 25 percent mortar waste.
  • Plaster: internal 12 mm of 1 : 4 on the inside face of the external walls, both faces of the partitions and the ceilings; external 20 mm of 1 : 3 on the outside faces and the parapet; 15 percent waste. The method is the one in the plaster calculator.
  • Cement and sand in the results are the block mortar and plaster added together (cement in 50 kg bags, rounded up once). The cement in the concrete is already inside the ready-mix.

Tiles and paint

  • Tiles: the net floor area of every floor, (L − 0.4) × (W − 0.4) minus the partitions, plus wall tiles in each wet room (taken as 2.0 × 2.5 m, tiled to 2.4 m with one door, 19.5 m² per room), plus 10 percent waste. Convert to boxes with the tile calculator.
  • Paint: internal walls (minus the tiled walls, taking each wet room as 2.0 × 2.5 m), ceilings and external faces, with 2 finish coats and 1 primer coat at 10 m² per litre and 10 percent waste. See the paint calculator.

Not included: excavation and backfill, stairs, water tank, septic tank, boundary and external works, waterproofing, gypsum ceilings, doors and windows, joinery, electrical, plumbing and AC works, kitchen units and sanitary ware.

Worked example

A ground floor annex of 10 × 8 m with 4 rooms (majlis, bedroom, bathroom, kitchen), a floor height of 3.2 m, a 200 mm slab, 6 windows, 3 internal doors, 1 external door, 2 wet rooms, columns every 4.5 m and a roof parapet. These are the default values of the calculator.

  • Column grid: 4 × 3 = 12 columns. Pads 12 × 1.2 × 1.2 × 0.5 = 8.64 m³. Blinding 12 × 1.4 × 1.4 × 0.1 = 2.35 m³. Columns 12 × 0.09 × 4.2 = 4.54 m³.
  • Beam run 4 × 8 + 3 × 10 = 62 m. Ground beams 62 × 0.3 × 0.5 = 9.30 m³. Floor beams 62 × 0.25 × 0.3 = 4.65 m³. Roof slab 10 × 8 × 0.2 = 16.00 m³. Ground slab 10 × 8 × 0.15 = 12.00 m³.
  • Net concrete 57.48 m³. With 5 percent: 60.35 m³, which is 8 trucks of 8 m³.
  • Steel: 8.64 × 70 + 4.54 × 180 + 9.3 × 110 + 4.65 × 140 + 16 × 100 + 12 × 35 = 5,115 kg. With 5 percent: 5.37 tonnes.
  • Walls: perimeter 36 m. External 36 × 2.7 + 36 parapet − 6 × 1.8 − 2.1 = 120.3 m². Partitions: 18 m × 3.0 − 3 × 2.1 = 47.7 m². Total 168 m² × 11.614 = 1,951 blocks, which is 2,049 with 5 percent.
  • Cement and sand for block mortar and plaster: about 4,085 kg, so 82 bags of 50 kg, and 10.0 m³ of sand (about 16 tonnes).
  • Tiles: floor 71.2 m² + wet-room walls 39.0 m² = 110.2 m², so about 121 m² with 10 percent.
  • Paint: 393 m² (inside and outside) gives about 86 litres of finish and 43 litres of primer.

The two other examples are a majlis annex of 8 × 6 m (about 39.8 m³ of concrete, 1,296 blocks) and the same annex with a first floor (about 97.6 m³ of concrete, 4,124 blocks).

Notes for Dubai and the UAE

  • Annex and extension works need an approved building permit from Dubai Municipality (or the relevant authority in the other emirates), with structural drawings by a licensed consultant. The structure, bar schedule and concrete grade come from those drawings, not from this estimate.
  • Structural work follows the Dubai Building Code and the standards it refers to. Foundation type and size depend on the soil investigation report of the plot, so the pad sizes here are placeholders for a first estimate.
  • Ready-mix concrete is ordered by the cubic metre from a batching plant and delivered in mixers of about 6 to 9 m³. Tell the supplier the grade, the slump, the pour date and the pump if needed. Concrete in the UAE is often called باطون in daily speech, while خرسانة is the common technical word.
  • Concrete blocks (طابوق, also called بلوك or طوب) in the UAE are commonly 400 × 200 mm on the face, in 100, 150 and 200 mm thickness. Check your block size with the supplier and the specification.
  • In hot weather keep fresh concrete, mortar and plaster damp (curing) as the consultant instructs, and avoid pouring in the midday sun.
  • Utility connections, for example the DEWA load for the annex, are separate from these quantities.

This tool counts quantities only. To turn them into a full cost for your annex, use the calculator in our app.

Frequently asked questions

What is a BOQ and what does this estimate give me?

A BOQ (bill of quantities) lists every material and work item of a project with its quantity. This tool gives the main material quantities of an annex early, before the full BOQ is prepared from the drawings: concrete, steel, blocks, cement and sand, tiles and paint. It does not give prices.

How much concrete does an annex need?

For a 10 × 8 m ground floor annex with a ground slab, about 57 m³ net (60 m³ to order) with the default assumptions, which is around 0.72 m³ per m² of built area. A first floor adds a slab, columns and beams. The structural drawings give the exact volume.

How much steel does an annex need?

The default annex above gives about 5.4 tonnes, around 64 kg per m² of built area. Real figures vary with the design. Use the steel level option to see a lighter or heavier case, and the rebar calculator once you have the bar schedule.

How many blocks do I need for an annex?

The number depends on the wall area. A 10 × 8 m annex with a parapet and 4 rooms needs about 2,050 blocks of 400 × 200 mm. Enter the measured partition length from the plan for a better number.

Does this include cost?

No. It gives quantities only. The cost calculator is in our app, and you can also request a quote through the button below.

Is the result exact?

It is a planning estimate. The approved drawings and your engineer always govern the final quantities.