Use this steel weight calculator to find the weight of reinforcement bars in kilograms and tonnes, build a bar bending schedule for slabs, beams and columns, and see how many 12 m stock bars to order after laps and off-cuts. It gives quantities only, in metric units, set up for villa and annex work in Dubai and the UAE.
How the steel weight and bar schedule are calculated
Weight per metre. A round bar weighs its cross-section area times the density of steel. For a bar of diameter d in millimetres: weight in kg per metre = π ÷ 4 × d² × 7850 ÷ 1,000,000, which is close to d² ÷ 162. A 12 mm bar weighs 0.888 kg per metre. The density of 7850 kg/m³ is the basis of the nominal masses in BS 4449 and ISO 6935, so the results match the usual weight tables.
Cut length of each bar mark.
- Slab or raft bars: length minus the cover at both ends. The number of bars per layer is the width minus the cover at both ends, divided by the spacing and rounded down, plus one. Use the quantity for the number of layers (for example bottom and top).
- Stirrups: the outer size of the stirrup is the section size minus the cover on each side. Cut length = 2 × (outer width + outer depth) + 2 hooks of 10 × d. Bend deductions are ignored, which errs slightly on the safe side. The number per member is the member length minus the cover at both ends, divided by the spacing and rounded down, plus one.
- Straight bars: the length you enter.
- Bars with a 90° hook at both ends: length between the hooks plus 2 × 12 × d (a typical 12 × d hook allowance, as in ACI 318 and BS 8666 practice; the bar schedule governs).
Laps. A bar longer than the stock length is built from several pieces. Each joint is a lap of the lap length (50 × d by default) and the lap adds steel: pieces = ⌈(run − lap) ÷ (stock − lap)⌉. The steel in the laps is included in the net weight. A run only a few millimetres over the stock length still needs a splice, so shorten the cut or order longer bars.
Stock bars and waste. All pieces of one diameter are cut from stock bars (12 m by default) with a first-fit-decreasing plan: the longest pieces go first and every piece goes into the first bar that still has room. This is a good practical plan but not always the mathematical optimum. The extra allowance adds a percentage of whole bars on top (rounded to the nearest bar) for rejected bars, bending errors and site changes.
Rebar weight chart
| Diameter (mm) | kg per metre | kg per 12 m bar | Bars per tonne |
|---|---|---|---|
| Ø6 | 0.222 | 2.66 | 375 |
| Ø8 | 0.395 | 4.74 | 211 |
| Ø10 | 0.617 | 7.40 | 135 |
| Ø12 | 0.888 | 10.65 | 94 |
| Ø14 | 1.208 | 14.50 | 69 |
| Ø16 | 1.578 | 18.94 | 53 |
| Ø18 | 1.998 | 23.97 | 42 |
| Ø20 | 2.466 | 29.59 | 34 |
| Ø22 | 2.984 | 35.81 | 28 |
| Ø25 | 3.853 | 46.24 | 22 |
| Ø28 | 4.834 | 58.00 | 17 |
| Ø32 | 6.313 | 75.76 | 13 |
| Ø36 | 7.990 | 95.88 | 10 |
| Ø40 | 9.865 | 118.38 | 8 |
Values are rounded; bars per tonne is from the exact mass.
Worked example
A 12 × 6 m annex roof slab has 12 mm bars at 150 mm in both directions in two layers (cover 30 mm). Four beams of 5 m and 250 × 500 mm have Ø10 stirrups at 150 mm (cover 40 mm) and 16 bars of Ø16 and 5.6 m.
- Bars along the 12 m side: cut length 12,000 − 60 = 11,940 mm; (6,000 − 60) ÷ 150 = 39.6, so 40 bars per layer; 80 bars in two layers = 955.2 m = 848.0 kg.
- Bars along the 6 m side: 5,940 mm; (12,000 − 60) ÷ 150 = 79.6, so 80 per layer; 160 bars = 950.4 m = 843.8 kg.
- Stirrups: outer 170 × 420 mm; 2 × (170 + 420) + 2 × 100 = 1,380 mm; (5,000 − 80) ÷ 150 = 32.8, so 33 per beam; 132 stirrups = 182.2 m = 112.3 kg (0.617 kg/m).
- Beam bars: 16 × 5.6 m = 89.6 m = 141.4 kg (1.578 kg/m).
- Net steel weight: 848.0 + 843.8 + 112.3 + 141.4 = 1,945.5 kg, which is 1.946 tonnes.
- Cutting from 12 m bars: 160 bars of Ø12 (one 11.94 m slab bar per 12 m bar, or two 5.94 m bars), 17 bars of Ø10 (8 stirrups per bar) and 8 bars of Ø16 (two beam bars per bar). With 3 percent extra: 165 + 18 + 8 = 191 bars, about 2,043 kg to order.
Notes for Dubai and the UAE
- The steel grade, cover, lap lengths, hooks and bar schedule are set in the approved structural drawings. Reinforcement is commonly grade B500B to BS 4449, or Grade 60 to ASTM A615 on some projects, but always use the grade the engineer states, and keep the mill test certificates for each delivery.
- Bars are normally supplied in 12 m lengths. Bar bending yards cut and bend to the engineer's schedule, so the quantities here help you check the order and plan deliveries.
- Dubai Municipality inspections and the supervising consultant check reinforcement (diameter, spacing, cover and laps) before every pour. Do not cast until the steel has been inspected and approved.
- Coastal and wet conditions need the cover and protection the drawings specify. The default covers here are only examples.
This tool measures steel weight and bar quantities only. For the cost of the whole annex, use the calculator in our app.
Frequently asked questions
How do I calculate the weight of a steel bar?
Weight in kg per metre is the diameter in millimetres squared divided by 162 (more exactly π ÷ 4 × d² × 7850 ÷ 1,000,000). Multiply by the length in metres and by the number of bars. For one 12 m bar of 12 mm, that is 0.888 × 12 = 10.65 kg.
How many 12 mm bars are in one tonne?
A 12 m bar of 12 mm weighs about 10.65 kg, so one tonne holds about 94 bars. The chart above gives the bars per tonne for every common diameter.
What is a bar bending schedule?
It is a table that lists every bar mark with its diameter, number of bars, cut length and weight. The fabricator cuts and bends from it, and the site team uses it to check deliveries. The calculator builds one for slab bars, stirrups, straight bars and hooked bars.
How much steel is wasted when cutting from 12 m bars?
It depends on the cut lengths. If the pieces fit the stock length well, off-cuts alone are 1 to 2 percent, and the default 3 percent allowance comes on top. If they leave awkward off-cuts, it can pass 10 percent. The calculator plans the cutting and shows the total waste so you can see it before you order.
How do I estimate the steel for a slab?
Add a slab or raft bars mark for each direction and layer, with the bar diameter and spacing from the drawings. The calculator counts the bars, applies the cover and shows the weight, the stock bars and the total in tonnes.
Does it show prices?
No. The tools on this page give quantities only. To price an annex, use the cost calculator in our app. The approved drawings and your engineer always govern the final quantities.