Work out how much concrete a footing, column, beam, slab or wall needs in cubic metres, add a waste allowance, and see how many ready-mix trucks to book. The calculator also gives the formwork area. It gives quantities only, in metric units, set up for villa and annex work in Dubai and the UAE.
How the concrete calculator works
Every element is converted to a volume in cubic metres (m³), multiplied by its quantity, and added up. Sizes in millimetres are divided by 1000 first.
- Slab or blinding: length × width × thickness.
- Isolated footing: length × width × depth.
- Strip footing: total length × width × depth.
- Square or rectangular column: width × depth × height.
- Round column: π × (diameter ÷ 2)² × height.
- Beam: length × width × depth below the slab.
- Concrete wall: length × thickness × height.
The order volume is the net volume plus the waste allowance (5 percent by default). The number of trucks is the order volume divided by the truck size, rounded up. Formwork is the contact area of the shuttering: slab soffits, column and beam faces, and the sides of footings and walls.
Worked example
A small annex has 6 isolated footings of 1.5 × 1.5 m and 0.6 m deep, and one roof slab of 10 × 8 m and 200 mm thick.
- Footings: 6 × 1.5 × 1.5 × 0.6 = 8.10 m³
- Slab: 10 × 8 × 0.2 = 16.00 m³
- Net volume: 24.10 m³
- With 5 percent waste: 24.10 × 1.05 = 25.31 m³ to order
- Trucks of 8 m³: 25.31 ÷ 8 = 3.16, so 4 trucks (three full and a last load of about 1.3 m³)
- Formwork: footing sides 21.6 m² plus slab soffit 80 m² = 101.6 m²
Notes for Dubai and the UAE
- Concrete grades, cover and mixes are set in the approved structural drawings and specification. Order the grade the engineer specifies, and ask the supplier for a delivery ticket for every truck.
- Dubai Municipality inspections and the supervising consultant normally require the concrete to be sampled and tested during the pour. Agree who takes the samples before the day.
- Hot-weather concreting rules apply in the summer months. Pours are often planned for the early morning or the evening, and the engineer sets the temperature limits.
- Ready-mix trucks in the UAE commonly carry between 6 and 10 m³. The default here is 8 m³: change it to the size your supplier uses.
- Check access for the truck and the pump before you book. Narrow villa streets and walls can limit what can reach the plot.
This tool measures concrete volume only. For the cost of the whole annex, use the calculator in our app.
Frequently asked questions
How do I calculate concrete in cubic metres?
Multiply length, width and thickness in metres to get the volume of each element, then add the elements together. For a slab 10 m by 8 m and 200 mm thick, that is 10 × 8 × 0.2 = 16 m³.
How much extra concrete should I order?
Most people add 3 to 10 percent for spillage, uneven ground and formwork movement. The calculator uses 5 percent by default and you can change it. Complex pours or pumped concrete may need more.
How many ready-mix trucks do I need?
Divide the order volume by the truck size and round up. The last truck is usually only part full, so tell the supplier the exact volume. Truck sizes differ between suppliers, so edit the truck size in the calculator.
Does this calculator give cement, sand and aggregate?
No, it gives the concrete volume only. Ready-mix is ordered by grade and volume, so you rarely need bags of cement. For site-mixed concrete, use a mix ratio calculator to turn the volume into cement, sand and aggregate.
Does it show prices?
No. The tools on this page give quantities only. To price an annex, use the cost calculator in our app.
Is the result exact?
It is a planning estimate based on the sizes you enter. The approved drawings and your engineer always govern the final quantities.