Use this formwork calculator to work out the shuttering area for footings, columns, beams, slabs and walls, how many plywood sheets to buy, and about how many props the slab and beams need. Enter the elements as they are on your drawings, for example a roof slab of 8 × 6 m with its beams and columns, and read the contact area in m², the sheets with cutting waste and reuse, and the props. Formwork is called شدة خشبية, قوالب or شدات in Arabic and shuttering in many contracts. It gives quantities only, in metric units, for villa, annex and boundary wall work in Dubai and the UAE.
How the formwork calculator works
Formwork area is the contact area: the surface of the plywood that touches the concrete. Each element is measured face by face, all sizes in metres (the mm fields are divided by 1000).
- Slab: soffit length × width, plus the edge forms 2 × (length + width) × thickness (optional, on by default).
- Beam: (width + 2 × depth below the slab) × length: the soffit and the two sides. The depth is measured below the slab so the part inside the slab is not counted twice. The beam soffit (width × length) also lies under the slab, so it is deducted from the slab soffit.
- Column: 2 × (width + depth) × height. Round column: π × diameter × height.
- Isolated footing: 2 × (length + width) × thickness: the four sides only, the base sits on the blinding.
- Strip footing: 2 × length × thickness (both sides).
- Concrete wall: 2 × length × height (both faces). Wall ends and openings are not counted.
- Plywood sheets = area × (1 + cutting waste) ÷ sheet area ÷ number of uses, rounded up. The common sheet is 2440 × 1220 mm (8 × 4 ft), which is 2.977 m². The cutting waste default is 10 percent. The uses default is 3: plain shuttering plywood is often reused 2 to 4 times and film-faced plywood more. The calculator also shows the sheets needed if every sheet is used only once.
- Slab props = (length ÷ spacing, rounded up, + 1) × (width ÷ spacing, rounded up, + 1) for each slab. This is a grid that includes the edge rows, which is on the safe side. The default spacing is 1.2 m.
- Beam props = beam length ÷ spacing, rounded up, per beam. The default is one every 1.0 m.
- Clear prop height = floor height − slab thickness − about 150 mm for the plywood, joists and prop head. It tells you which prop length range to ask for.
The prop spacing and the plywood reuse are planning assumptions, not rules. The real spacing depends on the slab thickness, the joist and plywood system and the load, and is set by the formwork designer or the supplier (temporary works are often specified by reference to BS 5975 and BS EN 12812). Columns, walls and footings are braced and tied, not propped, so no props are counted for them. Timber joists and bearers, tie rods, release agent, stair formwork and slab openings are not included.
Worked example: annex roof slab
The roof slab of a villa annex: slab 8 × 6 m and 200 mm thick, three beams of 8 m (250 mm wide, 400 mm below the slab) and six columns of 300 × 300 mm, 2.6 m high. Plywood 2440 × 1220 mm, cutting waste 10 percent, each sheet used 3 times, props on a 1.2 m grid, beam props every 1.0 m, floor height 3.0 m.
- Slab: soffit 8 × 6 = 48.0 m², edges 2 × (8 + 6) × 0.2 = 5.6 m², so 53.6 m².
- Beams: 3 × 8 × (0.25 + 2 × 0.4) = 25.2 m². Columns: 6 × 2 × (0.3 + 0.3) × 2.6 = 18.72 m².
- Overlap: the three beam soffits 3 × 8 × 0.25 = 6.0 m² are already part of the 48 m² slab soffit, so they are deducted once.
- Contact area: 53.6 + 25.2 + 18.72 − 6.0 = 91.52 m².
- Sheets: 91.52 × 1.10 = 100.67 m² ÷ 2.977 = 33.82, so 34 sheets if used once. With 3 uses: 100.67 ÷ (2.977 × 3) = 11.27, so 12 sheets.
- Slab props: (8 ÷ 1.2 = 6.67, so 7, + 1 = 8) × (6 ÷ 1.2 = 5, + 1 = 6) = 48. Beam props: 8 ÷ 1.0 = 8 per beam × 3 = 24. Total 72 props.
- Clear prop height: 3.0 − 0.20 − 0.15 = 2.65 m.
Two more real cases are loaded by the "Try an example" buttons. Twelve footings of 1.5 × 1.5 × 0.5 m with twelve neck columns of 300 × 300 mm, 0.7 m high, make 46.08 m² and 6 sheets with 3 uses (18 if used once). A retaining wall of 20 m, 2.5 m high with a 20 m strip footing 0.4 m thick makes 116 m² and 22 sheets with 2 uses (43 if used once).
Notes for Dubai and the UAE
- Plywood for shuttering is normally sold in sheets of 2440 × 1220 mm in thicknesses such as 12 and 18 mm. Film-faced (phenolic) plywood gives a better finish and more reuses. Check the thickness and grade with your supplier and the specification.
- The required concrete finish (ordinary or fair-faced) is set in the specification and changes how many times plywood can be reused. For fair-faced concrete expect fewer reuses.
- Falsework for slabs and beams is temporary works. The supplier or a competent person normally checks the spacing and the prop capacity for the slab thickness and the height. Do not pour on props that were chosen only from this estimate.
- The time before the soffit forms and props can be removed is set by the consultant and the specification. In Dubai heat concrete gains strength quickly, but curing must not be skipped. Follow the engineer's instructions.
- Formwork area is normally measured as contact area in a bill of quantities, so this number can help you check a contractor's figure. The concrete calculator also shows a formwork area, but it does not add slab edge forms, so the two can differ slightly for slabs.
This tool counts area, sheets and props only. For the cost of the whole annex, use the calculator in our app.
Frequently asked questions
How do I calculate the formwork area of a slab?
Multiply the length by the width for the soffit, and add the edge forms: the perimeter times the slab thickness. For a slab of 8 × 6 m and 200 mm that is 48 + 5.6 = 53.6 m². Beams and columns are added separately by their faces.
How many plywood sheets do I need for shuttering?
Divide the contact area (plus 5 to 15 percent for cutting) by the area of one sheet, 2.977 m² for 2440 × 1220 mm, and divide again by the number of times you can reuse each sheet. The calculator shows both the single-use and the reuse figure.
How many times can shuttering plywood be reused?
It depends on the plywood grade, the handling, the release agent and the finish required. Plain shuttering ply is often reused 2 to 4 times, film-faced plywood more. Reuse only works when the pours follow each other, so if you pour everything at once order close to the single-use figure.
How many props do I need for a slab?
It depends on the slab thickness, the joist system and the prop capacity, so the real number comes from the formwork designer or supplier. As a planning estimate the calculator uses a grid, 1.2 m by default, including the edge rows, plus one prop every 1.0 m under each beam.
Does the formwork area include the beam sides and the slab edges?
Yes. Beams count the soffit and both sides, measured below the slab, and the slab edge forms can be switched on or off. The area is the contact area with the concrete.
Is the result exact?
It is a planning estimate based on the sizes you enter. The approved drawings, the formwork design and your engineer always govern the final quantities.