- DEWA electricity connection for an annex in short
- Why plan electricity at the start of an annex project?
- Who applies for a DEWA connection: owner, consultant or contractor?
- DEWA building connection steps for a villa extension
- 1. Design and electrical drawings
- 2. One combined application
- 3. Design approval and connection cost
- 4. LV inspection
- 5. Supply terms, meter and supply release
- DEWA electrical drawings approval for a villa: documents to prepare
- What to settle in the design
- How long does a DEWA connection take? Times stated by DEWA
- Al Namoos: DEWA's connection for loads up to 150 kW
- DEWA LV inspection, meter installation and supply release
- DEWA connection fees: what DEWA states
- Does a villa annex get its own DEWA meter?
- Common reasons for delay in a DEWA connection
- How Al Mustafa Contracting coordinates the DEWA steps
- Frequently asked questions
- Can I apply to DEWA myself as the owner?
- Does a villa annex need a separate DEWA meter?
- How long does a DEWA connection take for a small villa load?
- How much does DEWA charge for the connection?
- When should the electrical drawings be approved?
- What is Al Namoos?
- Who signs DEWA's supply terms?
- Need help planning the electrical side of your annex?
- Official sources
A DEWA electricity connection for a villa annex (also called a service block) in Dubai is requested through one online application, submitted by a DEWA-enrolled consultant or contractor, and it goes smoothly when the electrical design is planned together with the architecture rather than after the walls are up. This guide follows DEWA's own pages: who applies, which documents the engineer prepares, the times DEWA states, what the inspection involves and how the connection cost is shown.
DEWA electricity connection for an annex in short
- DEWA bundles the Building NOC - Electricity and the electricity connection into a single application. The output is the approved Building NOC - Electricity, the design approval and the estimated invoice.
- Only DEWA-enrolled consultants and contractors can submit it. The owner assigns one and does not apply directly. Projects licensed by Dubai Municipality are submitted through the Dubai Building Permit System (DBPS), and DEWA receives them by digital integration.
- DEWA states these times: Building NOC 2 working days, LV design approval 1 to 3 working days depending on the load, and LV inspection 1 working day.
- For loads up to 150 kW, DEWA's Al Namoos service lets a contractor complete the connection in two steps within 5 days.
- The application itself is free. The connection cost is shown after design approval and is valid for one year. This guide quotes no rates.
- Whether an annex gets its own DEWA meter is not stated on DEWA's pages. It is decided in the approved electrical design.
Why plan electricity at the start of an annex project?
The electrical drawings decide things that are hard to move later: where the distribution board sits, where the meter and electrical room go, how the cable reaches the annex and what total load the building will carry. The same advice appears in our MBRHE guide: get the electrical drawings approved at the start of the project, not at the end. The permanent meter and the final electrical inspection come last, so any delay there holds up handover.

It also helps to keep the electrical design in step with the building permit. For the Dubai Municipality side, read our guide to the building permit for an annex or majlis and the Dubai Building Code guide.
Who applies for a DEWA connection: owner, consultant or contractor?
DEWA's page says the application is online only and that only enrolled consultants and contractors can submit it. In practice each party has a clear role:
| Party | What they do |
|---|---|
| Owner | Assigns the enrolled consultant or contractor, provides the project details, pays the connection invoice and signs DEWA's supply terms before the supply is released. |
| Consultant | Prepares the electrical drawings, load schedule and premise details sheet, and submits the application if enrolled. |
| Contractor | Installs to the approved design and requests the LV inspection when the installation is complete. |
| DEWA | Approves the design, issues the connection cost, inspects, installs the meter and releases the supply. |
The application is made on the DEWA website or the Build in Dubai app. If the project is licensed by Dubai Municipality, it goes only through DBPS, with no separate DEWA request. For other authorities, such as free zones, the application is made through DEWA channels.
DEWA building connection steps for a villa extension
1. Design and electrical drawings
The engineer prepares the documents DEWA lists (see the next section) based on the approved architectural layout. Agree the annex's air conditioning, kitchen and other major loads early, because the total connected load drives the design and the cost.
2. One combined application
The enrolled consultant or contractor submits a single application that covers the Building NOC - Electricity and the connection. DEWA states the Building NOC at 2 working days.
3. Design approval and connection cost
After design approval DEWA issues the estimate and invoice for the connection. The owner receives the notification and pays through DEWA's payment channels.
4. LV inspection
When the site is ready and the installation and wiring are complete, the inspection is requested through the DEWA website. The result is given on the spot: approved, or a snag list to fix.
5. Supply terms, meter and supply release
The owner signs DEWA's Terms and Conditions for Supply of Electricity - Water. DEWA then confirms the date for meter installation and supply release.

DEWA electrical drawings approval for a villa: documents to prepare
These are the documents DEWA lists for the application, in short. Your engineer works from the current list on DEWA's page.
| Document | What it shows |
|---|---|
| Setting-out plan | The plot and building position, with the meter location when the load is under 400 kW. |
| Load summary | Total connected load, MDB and SMDB schedules, and maximum demand including the number of kWh meters. |
| Single line diagram | The LV distribution and the tariff metering. |
| Layout plans | Site layout and ground floor plan showing the LV room, kWh meter and MDB. |
| Room details | Dimensions of the electrical room or cupboard. |
| Wiring layouts | Lighting and power. |
| Premise details sheet | DEWA's template, filled in for the building. |
| Site photo | Submitted with the LV inspection request. |
DEWA also publishes its regulations for electrical installations, which your engineer checks when designing; the 2017 edition is listed on DEWA's builder menu.
What to settle in the design
- Load: list the air conditioning, kitchen, water heating and any future additions, so the approved load is realistic.
- Distribution board: a location that stays accessible and fits the room dimensions on the drawings.
- Cable route: from the supply point or the main villa board to the annex, agreed with the site layout and landscaping.
- Meter: its position, and whether the annex shares the villa meter or has its own (see below).
How long does a DEWA connection take? Times stated by DEWA
| Step | DEWA's stated time |
|---|---|
| Building NOC | 2 working days |
| LV design approval, 1 to 150 kW | 1 working day |
| LV design approval, 151 to 400 kW | 2 working days |
| LV design approval, 401 kW and above | 3 working days |
| Connection cost issued, Al Namoos | 1 working day |
| Connection cost issued, other projects | 3 working days |
| LV inspection | 1 working day from submission |
These are the times DEWA states. They do not include preparing the drawings, answering comments, building the installation or fixing a snag list, which is why the electrical design is best started together with the architecture.
Al Namoos: DEWA's connection for loads up to 150 kW
Al Namoos is DEWA's fast permanent connection. It is exclusively for contractors, for new permanent connections with a load up to 150 kW supplied from DEWA's existing network, and DEWA describes it as two steps within 5 days. The contractor applies for the low-voltage inspection, and DEWA then carries out the external work, installs the meter and makes the final connection after the connection fee is paid. Ask your contractor or engineer whether your project qualifies. DEWA's Al Namoos page lists the enquiries line on 04 322 9999.
DEWA LV inspection, meter installation and supply release
The LV inspection is requested after site readiness and after the connection invoice is paid. DEWA gives the result on the spot, either approved or a snag list. Once approved, DEWA confirms the date for meter installation and supply release. The owner's signature on the supply terms is needed before the supply is released, so have it ready.

DEWA connection fees: what DEWA states
The e-service application is free. The connection itself is not: DEWA issues an estimate and invoice after design approval, and it is valid for one year from issue. The cost is calculated on the approved total connected load using a slab unit rate per kW, regardless of cable length or route. If the plot already has a connected load, the slab starts from the existing load and only the proposed load is charged. DEWA publishes the rates on its connection cost calculator and shows the figure when the consultant or contractor applies, so we do not quote any number here.
Does a villa annex get its own DEWA meter?
DEWA's pages do not mention annexes, majlis or service blocks by name, so we cannot state a rule. Whether the annex shares the villa meter or gets its own follows the approved electrical design and DEWA's decision. Raise the question with your engineer at the drawing stage, because the meter position and the electrical room are part of the documents DEWA reviews. DEWA's builder FAQ says, in the context of its ASRA'A initiative, that changing the meter location after execution and supply release is not recommended and may revise the invoice.
Common reasons for delay in a DEWA connection
- The electrical drawings are left until the building is finished, so the electrical room or the distribution board position has to be changed.
- The load schedule changes after approval, for example when air conditioning is added.
- The LV inspection is requested before the installation and wiring are complete.
- The invoice is not paid before the inspection request, or the owner's supply terms are not signed in time.
- A snag list from the inspection is not closed quickly.
Adding load later, or needing temporary power during construction, follows the same DEWA guidelines according to DEWA's connection page; see our guides on increasing the electrical load and temporary construction power. If rooftop solar is planned, read Shams Dubai for villa owners.
How Al Mustafa Contracting coordinates the DEWA steps
We plan the electrical scope together with the owner, the engineering office and our engineers, so the drawings, the permit and the build move as one job. In practice that means agreeing the loads and the board and meter positions early, keeping the installation in line with the approved drawings, and telling the owner in good time when DEWA needs a signature or an inspection date. Our contractor checklist and guide to inspections and the completion certificate show where these steps sit in a project, and the cost guide explains what drives the budget. For a new home, see our villa construction in Dubai page.
Frequently asked questions
Can I apply to DEWA myself as the owner?
No. DEWA states that only enrolled consultants and contractors can submit the application, and that it is online only. You assign one of them and provide the project details.
Does a villa annex need a separate DEWA meter?
DEWA's pages do not state this for annexes. It follows the approved electrical design and DEWA's decision, so ask your engineer to settle it at the drawing stage.
How long does a DEWA connection take for a small villa load?
DEWA states 2 working days for the Building NOC, 1 working day for LV design approval up to 150 kW, up to 3 working days for the connection cost (1 working day under Al Namoos) and 1 working day for the LV inspection. Preparing the drawings and the installation come on top.
How much does DEWA charge for the connection?
The application is free. The connection cost is calculated per kW on the approved load, shown after design approval and valid for one year. We do not quote rates; DEWA shows the figure when you apply.
When should the electrical drawings be approved?
At the start of the project, not at the end, so the permanent connection does not delay handover.
What is Al Namoos?
DEWA's fast permanent connection for contractors, for loads up to 150 kW from the existing network, in two steps within 5 days.
Who signs DEWA's supply terms?
The owner signs the Terms and Conditions for Supply of Electricity - Water before the supply is released.
Need help planning the electrical side of your annex?
We are happy to look at your plot and plans and explain how the DEWA steps fit your project. Message us on WhatsApp, use the contact page, try the free cost calculator or browse our projects.
This article summarises official DEWA pages for owners and is not legal advice. The official DEWA website and its current requirements prevail.
Official sources
- DEWA: Getting Electricity Permits and Connections (Building NOC - Electricity and electricity connection)
- DEWA: Al Namoos, fast electricity connection for loads up to 150 kW
- DEWA: Electricity Connection Cost Calculator
- DEWA: Builder FAQ
- DEWA: Regulations for Electrical Installations, 2017 Edition