This villa electrical load calculator answers the question every owner and contractor asks before applying to DEWA: how big is my connected load, what maximum demand should I expect, and which supply size should I ask about? Enter the lighting points, sockets, air conditioners (in tons) and fixed appliances of your villa, annex or majlis, or tap one of the examples. It is a preliminary estimate: the final load schedule is prepared by a DEWA-registered electrical consultant. It gives loads and sizes only, no costs.
How the electrical load is calculated
The tool follows the order of the DEWA Regulations for Electrical Installations (2017 edition), section 4.7, "Assessment of connected load and maximum demand".
- Lighting and fans (4.7.1): number of points × watts per point. DEWA says to take at least 100 W per point when the fittings are not selected yet.
- 13 A sockets (4.7.1): number of socket points × 200 W, the DEWA minimum for a general utility socket. A twin socket counts as two points. Kitchen appliances, heaters and AC are not left to the sockets: enter them separately.
- Air conditioning and fixed appliances (4.7.1): the actual load of each appliance. The tool turns tons into electrical kW with 1.5 kW per ton by default (a typical 1.2 to 1.8 for a tropical-rated split unit); if you have the nameplate input power, use it.
- Connected load = lighting + sockets + AC + appliances, with no demand factor. DEWA 4.7.2 states that distribution boards are rated for the total connected load before a demand factor is applied.
- Estimated maximum demand = each group × its factor, added up, plus a future allowance (10 percent by default). DEWA 4.7.2 allows a demand factor (allowance for diversity) "worked out by a suitably qualified electrical engineer" at main and sub-main level, The 10 percent future allowance is a planning value: the Appendix 5 notes only ask that future demand is considered when sizing circuits. DEWA does not publish factors for villas, so the factors here are typical planning values: lighting 0.66, sockets 0.40, AC 1.00 (you can lower it), water heaters 0.75, cooker 0.6, washer and kitchen appliances 0.5, pumps 0.7, pool 0.8, EV charger 1.0, lift 0.5.
- Design current (three-phase, 400 V) = demand in W ÷ (√3 × 400 × power factor), with a power factor of 0.9 by default.
- Supply band: the smallest feeder in DEWA's guidance list (4.7.2) whose maximum demand limit is at or above your estimate: 60 A for 30 kW, 100 A for 50 kW, 125 A for 60 kW, 160 A for 80 kW, 200 A for 100 kW, 300 A for 150 kW, 400 A for 200 kW. This is a band to discuss with DEWA, not a decision.
Only the 100 W and 200 W minimums, the "actual load" rule and the feeder limits come from the DEWA regulations. The demand factors and the typical appliance ratings (water heater 3 kW, cooker 7 kW, pool pump 2.2 kW, EV charger 7.4 kW, and so on) are planning values you can overwrite with the real nameplate figures.
Worked example: an annex of about 80 m²
An annex with two bedrooms, a majlis and a small kitchen: 24 lighting points of 100 W, 30 socket points, two 2-ton AC units and one 3-ton unit, two 3 kW water heaters, a 7 kW cooker, a 2.5 kW washing machine and a 1.5 kW pump. These are the default values, and the first example button.
- Lighting: 24 × 100 W = 2.4 kW. Sockets: 30 × 200 W = 6.0 kW.
- AC: (2 × 2 + 1 × 3) = 7 tons × 1.5 = 10.5 kW.
- Appliances: 2 × 3 + 7 + 2.5 + 1.5 = 17.0 kW.
- Connected load: 2.4 + 6.0 + 10.5 + 17.0 = 35.9 kW.
- Demand: 2.4 × 0.66 + 6.0 × 0.40 + 10.5 × 1.00 + (6 × 0.75 + 7 × 0.6 + 2.5 × 0.5 + 1.5 × 0.7) = 1.58 + 2.40 + 10.50 + 11.00 = 25.48 kW.
- Estimated maximum demand: 25.48 × 1.10 = 28.0 kW, about 78 percent of the connected load.
- Design current: 28 032 ÷ (1.732 × 400 × 0.9) = 45 A, so the 60 A band (30 kW guidance limit) is the one to ask DEWA about.
The other two examples are a 6 × 8 m majlis (16.7 kW connected, about 14 kW demand, still the 60 A band) and a five-bedroom G+1 villa with a pool and an EV charger (121.6 kW connected, 92 kW demand, 148 A, the 200 A band).
Notes for Dubai and the UAE
- DEWA confirms the supply. The regulations (section 3.1) require the owner to obtain DEWA's confirmation that power is available before construction starts, and the supply is confirmed in the No Objection Certificate. A total connected load above 400 kW normally needs space for a DEWA substation inside the plot.
- The consultant signs the load schedule. DEWA's load distribution schedule formats are in Appendices 2, 3 and 4 of the regulations. The consultant chooses the demand factor and shows it on the drawings. Another method is allowed if the consultant submits it with the proposed diversity at each level.
- The meter sits in the compound wall. For a villa the metering cabinet with the main incomer breaker is installed outside, recessed in the compound wall (section 3.2), with at least 2 m between the electricity and water service cabinets. Direct-connected meters are used up to 125 A. From 160 A DEWA uses CT-operated metering (DEWA circular of 2013, check that it is still current).
- Balance the phases. With a three-phase supply, spread lights, sockets, water heaters and single-phase AC evenly on the three phases (4.2.7).
- Sockets and small annexes. The tool counts 13 A sockets at 200 W. DEWA allows 500 W for a 15 A residential socket and 1000 W for a commercial one, so enter 15 A sockets as fixed appliances. The current assumes a 400 V three-phase supply; DEWA may supply a very small annex single-phase.
- Air conditioners need under-voltage relays with auto-reset (DEWA circular DP-VP-CS-GEN-0153-2021, which also allows them in the consumer distribution board for a group of units), and each room unit has its own final circuit (DEWA 4.6.6). Heavy AC load is what drives most Dubai villa demand, so check your AC tonnage with the AC size calculator.
- Solar and EV loads change the picture: see the Shams Dubai solar calculator, and enter an EV charger as a fixed appliance.
This tool estimates electrical load only. For the cost of the whole annex, use the calculator in our app.
Frequently asked questions
How do I calculate the electrical load of a villa?
Add the connected load of every group (lighting at least 100 W per point, sockets at least 200 W each, air conditioners and appliances at their actual rating), then apply demand factors to get the maximum demand. DEWA expects the final calculation from a registered consultant with a load schedule. This tool gives you the same steps for a quick, preliminary answer.
What is the difference between connected load and maximum demand?
Connected load is everything installed added together. Maximum demand is the most that is likely to run at the same time. It is lower because not every light, socket and appliance is on together. Distribution boards are rated for the connected load, while the supply and the main breaker are chosen from the maximum demand.
How many kW does a typical Dubai villa need?
It depends on the size, the AC and the extras. In the examples above, an 80 m² annex has about 36 kW connected and 28 kW demand, and a five-bedroom villa about 122 kW connected and 92 kW demand. AC is the biggest part, so a bigger or less efficient AC system pushes the demand up quickly.
How many amps is my DEWA supply?
The tool shows the design current and the smallest feeder band in DEWA's guidance (60, 100, 125, 160, 200, 300 or 400 A). DEWA decides the actual supply when it issues the No Objection Certificate, so treat the result as the figure to discuss with your consultant.
Can I use this for the DEWA submission?
No. It is a planning tool. The load distribution schedule submitted to DEWA must come from a DEWA-registered electrical consultant, using the DEWA formats and the approved drawings.
Does it show prices?
No. The tools on this site give quantities and sizes only. To price a project, use the cost calculator in our app.