Rebar Cutting Optimizer (Steel Bar Cutting Plan)

This rebar cutting optimizer turns your cutting list (bar diameter, cut length and number of pieces) into a steel bar cutting plan from 12 m stock bars. Enter the bars you need, as they appear on the bar bending schedule, and you get the number of bars to order for each diameter, what to cut from every bar, the off-cut left, the waste percentage and the steel weight to order. It gives quantities only, in metric units, for villa, annex and boundary wall work in Dubai and the UAE.

How the cutting plan is calculated

Cutting list. Each line is a bar diameter, a cut length and a number of pieces. Use the first type when the schedule already gives the cut length. Use the second type for a bar with a 90° hook at both ends: the length you enter is between the hooks and the tool adds 2 × 12 × d for the hooks (a typical 12 × d allowance, as in ACI 318 25.3 and BS 8666 practice; the bar schedule governs).

Long bars and laps. A piece longer than the stock bar (for example 30 m of boundary wall steel) is split into stock bars with lap splices of 50 × d by default: pieces = ⌈(run − lap) ÷ (stock − lap)⌉. The lap steel is counted in the net weight. Take the real lap length from the drawings.

Cutting plan. Pieces of different diameters are never mixed. For each diameter the tool uses a best-fit decreasing rule: pieces are placed longest first, each in the bar whose free length fits it most tightly. A second pass then tries to empty the least-filled bars by moving their pieces into the free space of the others. When a diameter has only a few different lengths, the tool also runs an exact search over cutting patterns and keeps whichever plan uses fewer bars. The result is deterministic, so the same list always gives the same plan. This is a very good practical plan, but cutting stock is a hard mathematical problem and the plan is not guaranteed to be the absolute optimum on a long, varied list.

Checks shown with the result. The theoretical minimum is the total length divided by the stock length, rounded up. Even a perfect plan cannot use fewer bars. The tool also shows how many bars you save compared with cutting every length from its own bars without mixing.

Weights. Weight per metre = π ÷ 4 × d² × 7850 ÷ 1,000,000, the basis of the nominal masses in BS 4449 and ISO 6935 (Ø12 = 0.888 kg/m). Steel to order = bars × stock length × weight per metre. The optional extra allowance adds a percentage of whole bars on top of the plan for rejected bars and bending errors.

Rebar weight chart

Diameter (mm)kg per metrekg per 12 m bar
Ø60.2222.66
Ø80.3954.74
Ø100.6177.40
Ø120.88810.65
Ø141.20814.50
Ø161.57818.94
Ø181.99823.97
Ø202.46629.59
Ø222.98435.81
Ø253.85346.24
Ø284.83458.00
Ø326.31375.76
Ø367.99095.88
Ø409.865118.38

Worked example: annex frame cutting list

The one-tap examples above fill the calculator with typical lists for Dubai villa work. They are illustrative lists to show how the tool works, not taken from a real project, so replace them with the lines of your own bar schedule. The first one is a typical villa annex frame list.

  • Ø16: 12 bars of 5.85 m (beam bottom bars), 16 bars of 3.20 m (column bars) and 8 bars of 2.40 m. Total length 140.6 m, which is 11.7 stock bars, so at least 12.
  • Plan for Ø16: 6 bars cut as 2 × 5.85 m (0.30 m off-cut); 5 bars cut as 3 × 3.20 m + 1 × 2.40 m (no off-cut at all); 1 bar cut as 1 × 3.20 m + 3 × 2.40 m. That is 12 bars, the theoretical minimum. Cutting each length on its own would need 14.
  • Ø12: 24 bars of 4.10 m, 30 bars of 2.35 m and 40 bars of 1.20 m. Total 216.9 m, so at least 19 bars. The plan uses 19 bars (against 22 without mixing), for example 12 bars of 2 × 4.10 m + 1 × 2.35 m + 1 × 1.20 m.
  • Total: 31 bars of 12 m (against 36 without mixing), 430 kg to order, 414.5 kg in the structure, waste 3.5 percent.

Boundary wall 30 m long, 2.4 m high

Assumptions (illustrative): three horizontal runs of Ø12, each 30 m long, and vertical Ø12 bars at 0.7 m centres (44 bars), each 2.40 m of wall height plus 0.60 m embedded in the foundation, so 3.00 m. Each 30 m run needs laps of 0.60 m (50 × d): 12.00 m + 12.00 m + 7.20 m. Result: 20 bars of 12 m. The verticals pack perfectly at 4 × 3.00 m per bar, the 12 m runs use 6 bars whole, and each 7.20 m piece shares its bar with a 3.00 m vertical. Steel to order 213 kg, in the wall 200 kg, waste 6 percent. Mixing lengths saves nothing here because the lengths already divide the bar well.

Majlis 6 × 8 m slab

Assumptions (illustrative): bottom mat of Ø12 at 150 mm centres in both directions with 25 mm cover at each end, so 41 bars of 7.95 m and 54 bars of 5.95 m. Top steel of Ø10 at 150 mm centres over the supports: 108 bars of 1.80 m over the two long beams and 82 bars of 2.20 m over the two short beams. Result: Ø12 needs 68 bars (the 7.95 m bars leave a 4.05 m off-cut that no bottom bar can use, and the 5.95 m bars go two to a bar), and Ø10 needs 32 bars (24 of them cut exactly as 3 × 2.20 m + 3 × 1.80 m = 12.00 m). Total 100 bars, 961 kg to order, 806 kg in the slab, waste 16 percent. The result is well above the theoretical minimum of 86 bars because the 4.05 m off-cuts of the Ø12 bars are in a different diameter from the short top bars. About 166 m of Ø12 off-cuts can go to spacers, chairs and ties, or your bar yard may be able to detail the long bars with a lap so that less is wasted, if the engineer approves.

Notes for Dubai and the UAE

  • Reinforcement is normally supplied in 12 m bars. Many projects order cut and bent steel from a bar bending yard, which plans its own cutting. Use this tool to check the quantity in a quotation and to plan the loose bars for site.
  • The grade, cover, laps, hooks and the bar bending schedule come from the approved structural drawings. Keep the mill test certificates of every delivery, and do not change bar sizes or lengths without the consultant's approval.
  • Keep off-cuts of 1 m or more for spacers, ties and small works instead of treating them as scrap, but never use them in a place where the drawings ask for a full-length bar or a lap of a given length.
  • The supervising consultant and Dubai Municipality inspections check the reinforcement before each pour. The quantity here is for ordering; the inspection checks what is fixed.

This tool measures bars and steel weight only. For the cost of the whole annex, use the calculator in our app.

Frequently asked questions

How do I reduce waste when cutting rebar from 12 m bars?

Mix the lengths. Put long and short pieces together on the same bar so that the off-cut of one is the piece of another, for example 3 × 3.20 m + 1 × 2.40 m = 12.00 m. The optimizer does this for you and shows how many bars the mixing saves compared with cutting each length on its own.

How many bars of 12 m do I need for a given cutting list?

At least the total length of all pieces divided by 12 m, rounded up, and in practice a few percent more because pieces do not fill the bars perfectly. Enter every line of the list and the calculator gives the number of bars per diameter and in total.

Is the plan the mathematical optimum?

It is a best-fit decreasing plan with an improvement pass. On many lists, especially short pieces that pack well, it reaches the theoretical minimum. Large pieces that cannot be paired, such as a 6.51 m bar on a 12 m stock bar, leave off-cuts that no plan can avoid, so the minimum is not always reachable. Cutting stock is a hard problem and the tool does not claim a guaranteed optimum on every list. The result card shows the theoretical minimum so you can judge the plan.

What happens to bars longer than 12 m?

They are split with lap splices. The tool uses 50 × the bar diameter by default and counts the extra steel in the laps. Take the lap length from your drawings and change it in the calculator.

How do I convert the number of bars into tonnes?

Multiply the bars by 12 m and by the weight per metre of the diameter (Ø12 is 0.888 kg/m, Ø16 is 1.578 kg/m). The calculator does it for you and shows kilograms and tonnes to order.

Does it show prices?

No. It gives quantities only. To price an annex, use the cost calculator in our app. The approved drawings and your engineer always govern the final quantities.