- Demolition permit in Dubai in short
- When do you need a demolition permit in Dubai?
- Who applies for the demolition permit?
- When a consultant is mandatory: circular 1-13-3 of 2025
- Disconnecting electricity and water with DEWA
- Site safety, surveys and neighbours
- Demolition waste: sorting, collection and disposal
- Insurance for demolition works
- Partial demolition and structural modification of a villa
- Excavation and shoring on a villa plot
- After demolition: completion certificate and the new building permit
- Demolition permit checklist for owners
- How Al Mustafa Contracting handles it
- Frequently asked questions
- Do I need a permit to demolish my villa in Dubai?
- Who applies for the demolition permit?
- Is a consultant required for a normal villa demolition?
- What happens to the electricity and water?
- How long is the demolition permit valid?
- Planning a demolition and a new build?
- Official sources
Before an old villa, annex or majlis in Dubai can be pulled down, even partly, the work needs a Dubai Municipality demolition permit, and the utilities have to be cleared with DEWA. This guide explains from the official documents when the permit is needed, who applies, what the site must have in place, how the waste is handled, what changes for a partial demolition and what happens next when you build the new house.
Demolition permit in Dubai in short
- Dubai Municipality (DM) offers a "Permit to Carry Out Demolition Works" for fully or partially demolishing a building. The service card describes it as valid for 3 months, and DM's rules say demolition may not start without it.
- For projects licensed by DM, the request goes through Dubai BPS, the Dubai Building Permit System. DEWA receives the utility request from that application, so the contractor does not file twice.
- For some building types a DM-licensed consulting office must be appointed first (circular 1-13-3 of 2025). A plain villa is not obviously on that list, but your engineer confirms how your building is classified.
- The demolition contractor must be registered and DEWA-enrolled, provide an insurance policy that runs until the demolition completion certificate, and follow DM's site safety and waste-sorting rules.
- A demolition permit does not authorise digging for the new building. The new villa, annex or majlis needs its own building permit.
- Fees are set by DM and DEWA and shown when the request is made, so this guide does not quote any figure.
When do you need a demolition permit in Dubai?
Local Order No. (3) of 1999 on regulating building works in Dubai counts demolition as construction work and says such works may not begin before the competent department has issued the relevant permit. Its schedule of permits lists a permit for demolishing a building and a separate one for demolishing a fence. The Order defines the applicant as the owner or the owner's legal representative.
The DM Safety Guide for Construction Works repeats the rule in its demolition chapter: no demolition work starts before a demolition permit is issued by the competent department. In practice that covers:
- pulling down an old villa completely in order to rebuild;
- removing a separate annex, majlis or outbuilding;
- demolishing part of a villa, such as a wing, a roof room or an old extension;
- removing the plot's boundary fence, which has its own permit type in the Order's schedule.
The DM service card covers full or partial demolition, and we found no small-job exemption in the documents we read. If your plot is in a free zone or a private development zone, the competent authority there may issue the permit instead, so confirm which authority applies to your plot first.
Who applies for the demolition permit?
The documents describe three roles, and which one files the request depends on the building.
- Owner: gives consent. DEWA's service asks for a letter from the owner, and Local Order 3 of 1999 defines the applicant as the owner or the owner's legal representative.
- Consulting office: for the building types listed in DM circular 1-13-3 of 2025, the owner must appoint a DM-licensed consulting office, of grade not lower than (G+12), as a condition of the permit. The circular says the office submits the permit request in Dubai BPS, appoints the demolition contractor, prepares a detailed demolition plan, supervises the work and checks that the contractor obtains the demolition completion certificate.
- Demolition contractor: DEWA states that DEWA-enrolled demolition contractors apply for the utility NOC. The Safety Guide says demolition and debris removal must be done by an approved, registered contractor, who submits a proposed method of work to DM for approval.
We did not find a public document that says whether, for an ordinary villa outside the circular's list, the contractor or an engineering office files the request in Dubai BPS. Ask your engineer or contractor to confirm this before you sign.
When a consultant is mandatory: circular 1-13-3 of 2025
DM circular 1-13-3 of 2025, dated 8 July 2025 and addressed to owners, consulting offices, contractors and demolition companies, requires a consulting office for these buildings:
- buildings higher than ground plus 12 floors;
- buildings with one or more basements, except a building with a single basement that is not attached to any building, service or street;
- buildings with specialised structural systems such as precast, post-tensioned or pre-stressed systems, villas excluded;
- buildings demolished with explosives;
- buildings whose demolition could endanger neighbours, including fire-damaged buildings or collapse incidents, and buildings next to heritage sites, water channels or metro and tram lines.
Two points matter for a villa owner. A villa with a basement beside the street or a neighbour's wall, or a plot next to a heritage site, can fall inside the list even though it is small. And the Safety Guide's own demolition chapter lists its consultant-supervision cases with a different height figure (ground plus 7 floors), which is another reason to let the engineer confirm what applies to your building instead of relying on a general rule.
Disconnecting electricity and water with DEWA
DEWA's "Demolishing Permits - Electricity/Water" service is a combined application for the demolition NOC for electricity and water and for the billing NOC. From the service page:
- Applicants are DEWA-enrolled demolition contractors.
- For projects that need a DM demolition permit, the request is made through Dubai BPS only. DEWA receives it through digital integration, so no separate DEWA application is needed. Projects licensed by other authorities apply through DEWA channels.
- The requirements are the online application and a letter from the owner. For a partial demolition DEWA also asks for a setting-out plan showing the demolition area. Submission is online only.
- DEWA lists the combined demolition approval at 10 working days.
- When electricity and water are deactivated the owner receives the final bill. After it is settled DEWA issues the clearance certificate and the services are disconnected.
The Safety Guide adds that electric, gas, water and sewer lines are shut off or capped outside the building line before demolition starts, and that the contractor checks the drawings against the real utility positions. For the power the new site will use afterwards, see our guide to temporary construction power from DEWA.
Site safety, surveys and neighbours
Chapter 13 of the DM Safety Guide sets the demolition rules, and our guide to construction site safety on Dubai villa works covers the wider rules that Decree No. (19) of 2025 makes binding. For demolition the Guide asks for:
- an engineering survey by a registered engineer of the structure and of the adjacent structures before the method is chosen;
- surveys for asbestos, lead and PCB-containing items, with written evidence given to the competent department, and asbestos removal by specialist contractors only;
- a demolition plan prepared by a registered engineer, with the method and sequence, and a method approved by DM that is not changed without telling the department;
- a fence at least 2 m high around the demolition area, warning signs before work starts, a restricted safe area around the site and security on site around the clock;
- a protection barrier toward adjacent buildings, as high as the building being demolished, and pedestrian safety built into the method;
- any part attached to a neighbouring building isolated first by hand-held tools for at least 3 m, and no demolition ball on parts attached to neighbours because of vibration;
Local Order 3 of 1999 makes the contractor and the engineer jointly responsible for damage to adjacent buildings and public utilities, and DM circular 3-1-2 of 2022 asks teams doing foundation excavation and shoring to check the condition of neighbouring buildings and choose methods that keep vibration low. We found no formal "notify the neighbours" step for demolition in the documents, but the Safety Guide asks for neighbouring buildings to be surveyed first, and speaking to your neighbours before the machines arrive is good practice.
Demolition waste: sorting, collection and disposal
DM circular 12-10-1 of 2023 requires waste to be separated and sorted on demolition sites before it goes to disposal sites. It gives the example of separating concrete and rebar, and removing removable parts such as doors, windows, aluminium, cables and metal sections. Contractors keep records of the sorted quantities, using the forms in Dubai BPS, and the supervising engineering office checks that this is done.
DM's technical guidelines on construction and demolition waste collection and transportation add that:
- collection and transport are done by companies licensed for that activity, with licensed vehicles tracked by DM's RASID system;
- site containers use colour codes for inert aggregates, metal, timber, dry recyclables, hazardous materials and general waste, and are labelled with the collector's name and licence number;
Insurance for demolition works
Executive Council Resolution No. (28) of 2022 asks the contractor to provide an insurance policy from a licensed insurer as a condition of the permit. The Resolution's list of covered works names demolition of buildings and works supporting the sides of excavations, with no area threshold for those two items. For demolition the policy runs from the permit date until the competent authority issues the completion certificate for the demolition. The Safety Guide adds that if the permit or the insurance expires, demolition may not continue, and both must be renewed before the expiry date.
Partial demolition and structural modification of a villa
Removing part of a villa is still a demolition. The DM service covers partial demolition and DEWA asks for the extra setting-out plan. The Safety Guide's extra conditions for partial demolition are the ones that protect the part you keep:
- utilities are isolated and moved out of the part to be removed;
- the engineer confirms that removing that part will not affect the stability of the remaining structure;
- demolition lines are set in structurally safe areas, and the remaining parts are shored and supported;
- where the part is connected to other buildings, the connection is isolated by hand-held tools to at least 3 m before any machine is used.
If you are altering a villa rather than removing a wing, for example opening a load-bearing wall or removing a slab, DM lists a separate "Permit to Make Modifications or Additions to Buildings", and the Resolution 28 insurance applies to additions and modifications of 300 m² or more. Structural changes should be designed and approved before the first wall is touched. Our guide to the Dubai building permit for a villa annex explains how modification requests work in Dubai BPS. If part of the building was altered without a permit, read about violations and fines for unlicensed building first.
Excavation and shoring on a villa plot
Demolition and digging are separate permits. The Safety Guide says the demolition permission does not allow excavation at the site for building purposes, and that when foundations are removed the excavation is refilled to ground level. Excavation and shoring for the new foundations belong to the new building permit. Resolution 28 also covers works supporting the sides of excavations.
After demolition: completion certificate and the new building permit
- Demolition completion: the circular for consulted cases asks the consulting office to check that the contractor obtains the demolition completion certificate through the established procedure, and Resolution 28 refers to the completion certificate for demolition. The step-by-step certificate procedure for a small villa was not in the public documents we read, so ask your engineer how it will be requested.
- Do not let the permit lapse: Local Order 3 of 1999 says a permit may be cancelled if works do not start within three months or stop for more than three, and DM lists a service to renew building and demolition permits where works have not started or have been stopped.
- New building permit: the new villa, annex or majlis is a separate request in Dubai BPS with its own drawings. See our guide to the building permit in Dubai and, for the final stage, Dubai Municipality inspections and the completion certificate.
Demolition permit checklist for owners
- Confirm with your engineer whether your building is on the consultant list in circular 1-13-3, and who files the request in Dubai BPS.
- Confirm that the demolition contractor is registered and DEWA-enrolled, and ask for the insurance policy and its expiry date.
- Ask for the engineer's survey, the asbestos and lead survey results and the demolition plan before work starts.
- Check the DEWA NOC and the deactivation, the final bill and the clearance certificate.
- Name the licensed waste collector and keep the sorting records.
- Plan the new building permit and the foundation work so the demolition permit does not expire.
How Al Mustafa Contracting handles it
We start with the plot, the old building and the plan for the new house, because the demolition and the new build should be planned as one project. With the owner and the engineering office we confirm which route applies, which licensed demolition contractor will do the work and what the permit and utility steps are. We then plan the new build around it: the order of work, the shoring and foundations, the temporary power and the neighbour protection. We do not promise approval times. Those are set by DM and DEWA.
Frequently asked questions
Do I need a permit to demolish my villa in Dubai?
Yes. Local Order 3 of 1999 counts demolition as construction work that needs a permit first, and DM offers a demolition works permit for full or partial demolition.
Who applies for the demolition permit?
The owner consents and the request is made in Dubai BPS. For the building types in circular 1-13-3 a DM-licensed consulting office files it. DEWA's utility NOC is requested by a DEWA-enrolled demolition contractor, or arrives through Dubai BPS for DM-licensed projects. Ask your engineer who files for your building.
Is a consultant required for a normal villa demolition?
Circular 1-13-3 lists the cases: buildings above ground plus 12 floors, buildings with basements (with an exception for a single detached basement), special structural systems other than villas, explosives and demolition that endangers neighbours. Your engineer confirms how your villa is classified.
What happens to the electricity and water?
The demolition contractor requests the DEWA NOC. The services are deactivated, you settle the final bill, DEWA issues the clearance certificate and the services are disconnected.
How long is the demolition permit valid?
DM's service card says 3 months. DM also has a service to renew a permit if the works have not started or have been stopped.
Planning a demolition and a new build?
We are happy to look at your plot and explain the steps before you appoint anyone. Message us on WhatsApp or use the contact page.
This article summarises official Dubai Municipality and DEWA documents for owners. The official websites and the current versions of the documents prevail, and your engineer confirms what applies to your plot.
Official sources
- Dubai Municipality: Circular 1-13-3 of 2025 (8 July 2025), appointing a consulting office for demolition permits of certain building types
- DEWA: Demolishing Permits - Electricity/Water
- Dubai Municipality: services list, Permit to Carry Out Demolition Works and Renew a Building or Demolition Permit
- Local Order No. (3) of 1999 Regulating Construction Works in the Emirate of Dubai
- Dubai Municipality: Safety Guide for Construction Works (Chapter 13, Demolition)
- Dubai Municipality: Circular 12-10-1 of 2023 on separating and sorting construction and demolition waste
- Dubai Municipality: Technical Guidelines on Construction and Demolition Waste Collection and Transportation Services
- Executive Council Resolution No. (28) of 2022 on the building works licence insurance policy
- Dubai Municipality: Circular 3-1-2 of 2022 on avoiding damage to neighbouring buildings from building projects