13 min read
In this article
- In short
- Build a house with MBRHE: grant, loan or both?
- MBRHE housing loan for a villa: who can apply and when
- MBRHE villa construction step by step
- Design and permit for a new home
- MBRHE villa construction: choosing the contractor and agreeing the contract
- Cost drivers and the bill of quantities
- Staged payments and Dubai Municipality inspections
- Documents to prepare
- VAT refund and handover
- Villa or annex: which guide do you need?
- Frequently asked questions
- How do I build a house with MBRHE?
- What is the MBRHE housing loan for a villa?
- Can I choose my own contractor for MBRHE villa construction?
- When are the payments released?
- Do I need an engineering office to build a villa?
- What does Dubai Municipality inspect on a villa?
- Is a villa different from an annex under MBRHE?
- Can I get a VAT refund on building my home?
- Need help planning your MBRHE villa construction?
- Official sources
MBRHE villa construction starts with a residential land grant and ends with a completion certificate, and in between the owner, a licensed engineering office, a contractor and the financing party each have a clear job. This guide explains how to build a house with MBRHE support in Dubai: which route fits, when to apply, how the contractor is chosen, how staged payments follow site progress and what Dubai Municipality inspects.
In short
- For MBRHE villa construction, MBRHE publishes separate services for a new home, for replacing an old home, and for maintenance or addition. An annex is not the same service as a new villa.
- For the building loan, MBRHE states that you apply after the land grant and the Dubai Municipality permit, and that you choose the contractor and the consultant.
- Payments go to the contractor by completion percentage, so a clear bill of quantities and a written contract matter most.
- Dubai Municipality asks for written consultancy and building contracts before work, and its engineer inspects before foundations and before a concrete roof slab are poured.
- Amounts and conditions belong to MBRHE; every figure here is quoted as published, so confirm it with MBRHE.
Build a house with MBRHE: grant, loan or both?
MBRHE's public service pages describe several routes, and the first step is to match your situation to the right one. MBRHE states a decision time of 15 working days for these services.
| Route | What MBRHE publishes |
|---|---|
| Building loan | Financing of up to AED 1,000,000 on a non-profit basis to build the family home on the residential land granted to you in the emirate. Payments are released to the contractor according to the percentage of work completed. |
| Building grant | After approval you submit the building permit, the architectural drawings and a valid building contract that covers every item needed for the completion certificate, or you choose execution through MBRHE. The contractor claims running payments online by completion percentage, approved by the owner and the consultant. |
| Replacement | A grant of up to AED 750,000 or a loan of up to AED 1,000,000 to rebuild an existing home that is worn out in whole or in part. |
| Maintenance or addition | Up to AED 300,000 for an existing home. This is the route most annexes and majlis follow; see our MBRHE annex and majlis guide. |
If your income changes after a loan is approved but before the funding file is opened, MBRHE says you can cancel the approval and apply for the building grant instead. For smaller works, see the MBRHE loan or grant funding guide.
MBRHE housing loan for a villa: who can apply and when
For the building loan, MBRHE lists these conditions. They are quoted from its published FAQ and can change, so treat them as a checklist for your conversation with MBRHE.
| Topic | As published by MBRHE |
|---|---|
| Applicant | A citizen holding a passport and a family book issued by Dubai, who has benefited from a residential land grant. |
| Income | Monthly income above AED 15,000 and not above AED 100,000, with total monthly deductions including the loan instalment not above 60% of income. |
| Land and permit | Land ready for building and a Dubai Municipality building permit issued. No completion certificate may have been issued yet. |
| When to apply | After the land grant and the building permit. You can still apply after work has started, provided it is not finished. |
| Security | The land is mortgaged for the loan term. |
| Extra cost | If the building cost exceeds the loan, you pay the difference before requesting the first payment. |
| Repayment start | After 18 months from approval, or one month after the final payment to the contractor, or at the completion certificate, whichever comes first. |
| Where to apply | The Emirati platform in the Dubai Now app, the Iskan app, the MBRHE website or the service centre. |
MBRHE adds that the funding file is opened at the Emirates Islamic housing finance centre (Nad Al Hamar branch) and that the financial solvency approval is valid for 60 days after the MBRHE approval, so have the contract ready in that window.
MBRHE villa construction step by step
Each step hands over to the next with a document. For the Dubai Municipality side, our Dubai building permit guide goes through every request type, and the inspections and completion certificate guide covers the last stage.
Design and permit for a new home
Start with a brief that fits what the financing can carry: bedrooms, majlis, kitchen, floors and finishing level. A licensed engineering office prepares the drawings and submits the permit request in Dubai BPS, Dubai Municipality's unified electronic window, which DM runs as three fixed steps of up to three working days each. The permit request in Dubai BPS shows which parties your project needs; for a new villa, plan to appoint a licensed engineering office, because MBRHE's funding file also asks for the consultancy licence and the manager's Emirates ID. Under Law 14 of 2025, nobody may contract an unlicensed firm for engineering consultancy.

Two points are worth raising with your engineer early. First, the ground: the Dubai Building Code asks for a soil investigation by accredited laboratories, with at least two boreholes for an individual villa, and the foundation level and soil bearing capacity are attached to the pre-pour request. Second, the rules for your plot: Dubai Municipality circular 2-3-1 of 2026 describes a "Home Priority" initiative for villas of UAE citizens, with conditions on setbacks and floor area, so ask whether your plot qualifies. Our Dubai Building Code guide explains where those rules live.
MBRHE villa construction: choosing the contractor and agreeing the contract
MBRHE states that the beneficiary chooses both the consultant and the contractor, and that the list of Dubai Municipality approved consultants and contractors is available on the Emirati platform in the Dubai Now app. A good fit is a contractor that is licensed in the right activity, builds from your approved drawings, and is comfortable working inside the financing party's process. Our approved contractors and materials guide explains how to check licences and approved materials, and the shell and core or turnkey guide compares the two ways a villa contract can be scoped.
The same circular lists the minimum clauses a villa contract should contain, and DM publishes guidance model contracts for both the building contract and the consultancy contract. A good contract names the parties, describes the works, sets the order of precedence of documents, shows the value and the payment schedule by stage, fixes the duration, and explains variations, delay, termination and disputes. MBRHE also asks for the contract signed by all parties, drawings with an area schedule and a bill of quantities signed by all parties.
Cost drivers and the bill of quantities
We do not quote prices, because a general number would mislead you. What helps is knowing what moves the cost. The main drivers are the built-up area and number of floors, the ground conditions and foundation design, the structure and roof type, the mechanical, electrical and plumbing scope, the level of finishes, the external works and the utility connections. Premium finishes often move the budget the most, so decide their level early.
The bill of quantities (BOQ) divides the contract into items such as excavation, foundations, structure, blockwork, services, joinery, tiling, paint and external works. To compare quotes, check that each covers the same scope, specifications and exclusions. MBRHE's rule that you pay any excess over the financing before the first payment makes this check worth doing before you sign, not after. Our villa cost factors guide goes driver by driver, and the free cost calculator app gives a first planning estimate that a site visit then confirms.

Staged payments and Dubai Municipality inspections
With the loan, the contracting company opens the funding file and payments then follow completion percentages. With the grant, MBRHE says the contractor submits running payments online, each not less than 10% of the grant value, approved by the owner and the consultant. In both cases, ask for the payment schedule, percentages and conditions in writing from day one.
Site progress and Dubai Municipality inspections run in parallel. DM limits its inspection of buildings during execution to the high-risk stages: foundation pouring, structure and building completion. The DM engineer inspects before the foundations are poured and before a concrete roof slab is poured, and casting waits for approval. A sandwich-panel roof has no pour, so the slab inspection does not apply to it.

Before the foundation pour, the contractor attaches the foundation level, the soil bearing capacity and the design assumptions to the Dubai BPS request so that DM engineers can check them first. Keep a photo record of every stage; it makes each payment approval simple.
Documents to prepare
| From | Documents |
|---|---|
| Owner | Passport, family book, land grant documents and plan, MBRHE approval, recent salary certificate or income proof, three-month account statement with IBAN. |
| Contractor | Valid trade licence, building permit, signed contract and BOQ, IBAN letter, manager's Emirates ID. |
| Engineering office | Valid consultancy licence, manager's Emirates ID, approved drawings with area schedule. |
MBRHE and the bank give the final list, so ask for it in writing and check the expiry dates; one missing paper can hold the file.
VAT refund and handover
MBRHE's FAQ points beneficiaries to the Federal Tax Authority's VAT refund service for UAE nationals who build new homes, available through the Emirates Tax portal. Conditions and deadlines are the Authority's, so confirm them there and keep your invoices organised.
At handover, we suggest that the final payment waits for the building completion certificate, which DM issues after inspecting that the works match the permit and approved drawings, and for the permanent service connections and the original warranties. DM's building order also bars occupation before the certificate and service connection without DM approval. Our inspections and completion certificate guide explains the final inspection in detail.
Villa or annex: which guide do you need?
If you are building a new home on granted land, this guide is your starting point, together with our guide to building a villa in Dubai. If you are adding a majlis, rooms or an annex to a home you already live in, the process and the MBRHE service are different, and the MBRHE annex and majlis guide is the better fit.

Frequently asked questions
How do I build a house with MBRHE?
Receive the residential land grant first, then prepare the design with a licensed engineering office and obtain the Dubai Municipality building permit. MBRHE states that you apply for the building loan after the land grant and the permit, and the contractor then opens the funding file.
What is the MBRHE housing loan for a villa?
MBRHE publishes a building loan of up to AED 1,000,000 on a non-profit basis for building the family home on the granted land, paid to the contractor by completion percentage. Confirm the current amount and your own eligibility with MBRHE.
Can I choose my own contractor for MBRHE villa construction?
Yes. MBRHE states that the beneficiary chooses the consultant and the contractor. The list of Dubai Municipality approved consultants and contractors is on the Emirati platform in the Dubai Now app.
When are the payments released?
By completion percentage. With the loan, the contracting company opens a funding file at the finance bank and payments follow progress. With the grant, MBRHE says running payments are submitted online and approved by the owner and the consultant.
Do I need an engineering office to build a villa?
DM documents treat the engineering office as the party that designs and supervises, and MBRHE's funding file asks for the consultancy licence. For a new villa, plan to appoint a licensed office, and let your permit request in Dubai BPS confirm the parties your project needs.
What does Dubai Municipality inspect on a villa?
DM limits its inspection during execution to the high-risk stages: foundation pouring, structure and completion. The DM engineer inspects before the foundations and before a concrete roof slab are poured. A sandwich-panel roof has no pour.
Is a villa different from an annex under MBRHE?
Yes. MBRHE lists a building loan and grant for a new home, a replacement service, and a separate maintenance or addition service for an existing home. Ask MBRHE which one matches your project.
Can I get a VAT refund on building my home?
MBRHE's FAQ refers beneficiaries to the Federal Tax Authority's VAT refund service for UAE nationals building new homes. Check the Authority's conditions before you start.
Need help planning your MBRHE villa construction?
We are happy to look at your land grant plot, your drawings or your idea and explain the path in plain language. Message us on WhatsApp, use the contact page, learn about our villa construction company in Dubai service, try the free cost calculator or browse our projects.
This guide is general information and is not legal advice. MBRHE publishes its own conditions and amounts, and the official websites and current versions of the documents prevail. Al Mustafa Contracting is an independent contractor and is not affiliated with MBRHE or any bank.
Official sources
- Mohammed Bin Rashid Housing Establishment: housing services and frequently asked questions (mbrhe.gov.ae), and the Federal Tax Authority: VAT refund for UAE nationals building new homes
- Circular 13-5-1 (2023): guidance contracts for engineering consultancy services and building contracts for villa projects
- Model guidance contract for building works (13-5-1-1) and Model guidance contract for engineering consultancy services (13-5-1-2)
- Circular 13-3-1 (2021): development of building licensing procedures and requirements for practising design and execution
- Circular 3-10-1 (2021): steps of building licensing, Circular 3-10-2 (2022): unified window for building licensing and Circular 11-4-1 (2021): pile, soil-bearing and foundation-level tests
- Law No. (14) of 2025 on regulating engineering consultancy activities and Law No. (7) of 2025 on regulating contracting activities in the Emirate of Dubai
- Local Order No. (3) of 1999 on regulating building works in the Emirate of Dubai and Circular 2-3-1 (2026): Home Priority initiative for villas of UAE citizens
- Dubai Building Code (2021 edition), Part K residential villas and soil investigation
Planning your next project?
Talk to the Al Mustafa team for advice and a quotation for your project in the UAE.



