Use this cement and sand calculator for the three questions asked on site: how many bags of cement and how much sand for a floor screed (area and thickness), how many for a given volume of mortar (mix ratio), and what your bags of cement will make and cover. You get whole bags of 50 kg, cubic metres and tonnes of sand, and the sand per bag in 20 litre buckets. Quantities only, in metric units, for villa, annex and majlis work in Dubai and the UAE.
How the cement and sand calculator works
- Floor screed: area (length × width of each room, minus anything you deduct) × thickness gives the screed volume. Add waste (default 10 percent for an uneven slab and spillage) to get the wet volume.
- Mortar: you enter the finished volume of mortar in m³ and the waste is added.
- Dry volume = wet volume × 1.33. Cement and sand pack together when wetted, so the dry materials take about a third more volume than the finished mortar (typical 1.25 to 1.35).
- Cement = dry volume ÷ (1 + sand parts) × 1,440 kg/m³, in bags of 50 kg rounded up. One bag is about 34.7 litres loose.
- Sand = dry volume × sand parts ÷ (1 + sand parts), taken as about 1,600 kg/m³ loose for the tonnes. Per bag of cement you need sand parts × 34.7 litres, shown in buckets of 20 litres.
- I have bags: N bags make N × 34.7 L × (1 + sand parts) of dry material, which is that ÷ 1.33 of wet mortar, less the waste. Divide by the thickness to get the area it covers.
The mix is cement : sand by volume. Common values are 1 : 3 or 1 : 4 for floor screed, 1 : 3 to 1 : 4 for bedding and 1 : 5 or 1 : 6 for lean fill and blockwork mortar, but the specification of your project governs. 1.33, 1,440 kg/m³ and 1,600 kg/m³ are common estimating values, not code requirements, and the same values are used in the plaster and block calculators. Water, admixtures, mesh and insulation are not counted.
Worked example: a majlis floor
A majlis of 8 × 6 m with a 50 mm unbonded cement-sand screed of 1 : 4 and 10 percent waste. These are the defaults of the calculator.
- Area: 8 × 6 = 48 m². Volume: 48 × 0.050 = 2.40 m³. With 10 percent waste: 2.64 m³ wet.
- Dry volume: 2.64 × 1.33 = 3.51 m³.
- Cement: 3.51 ÷ 5 × 1,440 = 1,011 kg = 20.2 bags, so 21 bags of 50 kg.
- Sand: 3.51 × 4 ÷ 5 = 2.81 m³, about 4.5 tonnes.
- Per bag of cement: 34.7 L × 4 = 139 litres of sand, about 7 buckets of 20 L. One bag covers about 2.4 m² at 50 mm.
Other tap-to-fill examples: 1.5 m³ of 1 : 4 mortar (13 bags and 1.76 m³ of sand), and "I have 20 bags" (2.78 m³ of sand, 2.37 m³ of mortar, 47.5 m² at 50 mm).
Notes for Dubai and the UAE
- Screed thickness depends on the type: bonded screed is usually 25 to 40 mm, unbonded 50 to 75 mm, and a floating screed over insulation 65 to 75 mm. For a screed to falls (roofs, bathrooms, balconies) enter the average thickness. The project specification governs.
- Use clean washed sand without too much silt or salt, which can cause cracking and efflorescence, and fresh cement from sealed bags.
- In hot weather the screed loses water too fast. Keep it damp (curing) as the consultant instructs and avoid laying it in direct midday sun.
- Screed over a waterproofing membrane is a protection screed: use the waterproofing calculator, which includes it. For tiles on top use the tile calculator.
- Damp sand from the pile bulks up, so measuring it by the bucket gives less sand than you think. Add about 10 to 25 percent, or measure dry sand.
- Cement and sand are delivered by the bag and by the truck, so order by the bag and by the tonne or cubic metre, with a little extra.
This tool counts cement and sand only. For the cost of the whole annex, use the calculator in our app.
Frequently asked questions
How many bags of cement for 100 m² of screed?
At 50 mm thick, a mix of 1 : 4 and 10 percent waste, 100 m² needs about 5.5 m³ of wet screed: 43 bags of 50 kg and 5.9 m³ of sand. At 40 mm it is about 34 bags. Use the calculator for your thickness and mix.
How do I calculate cement and sand for a mortar mix?
Take the volume of mortar you need, add waste, multiply by 1.33 for the dry volume and split it by the mix ratio. For 1 m³ of 1 : 4 mortar that is about 383 kg of cement (7.7 bags) and 1.06 m³ of sand.
How much sand goes with one bag of cement?
A bag of 50 kg is about 34.7 litres. In a 1 : 4 mix you need four times that, 139 litres, or about 7 buckets of 20 litres. In a 1 : 3 mix it is about 5 buckets. Add extra for damp sand.
What screed thickness and mix should I use?
Typically 25 to 40 mm bonded and 50 to 75 mm unbonded, in a 1 : 3 or 1 : 4 mix. The specification and the engineer decide, and a richer mix is not always better because it shrinks and cracks more.
What will my bags of cement cover?
Choose "I have bags", enter the bags, the mix and the thickness. For example 20 bags of 1 : 4 make about 2.4 m³ of usable mortar, which covers about 47 m² at 50 mm.
Is the result exact?
It is a planning estimate from the sizes you enter. The approved drawings and your engineer govern the final quantities.