Use this gypsum board calculator to turn a ceiling or partition into an order list: enter the length and width of a false ceiling, or the length and height of a partition wall with its doors, and get the number of 1.2 × 2.4 m boards, the main and furring channels, studs and track, hangers, screws, joint tape and joint compound. Tap one of the examples (a majlis ceiling, an annex partition, a double-layer corridor) to see how it works, then type your own sizes. Gypsum board is called جبس بورد in Arabic. It gives quantities only, in metric units, for villa, annex and majlis work in Dubai and the UAE.
How the gypsum board calculator works
All framing values below are typical for metal-frame drywall systems. The system supplier's data sheet and the approved drawings always govern.
- Boards = board face area ÷ board area × (1 + waste), rounded up. A 1.2 × 2.4 m board is 2.88 m². Face area counts every layer: ceiling area × layers, plus net partition area × faces × layers. The default waste is 10 percent for cutting.
- Net partition area = length × height of each partition, minus the door openings.
- Ceiling, size a × b (a is the longer side). Main channels run along a, every 1.2 m across b, with the first and last row within 300 mm of the wall: mains = ceil((b − 0.6) ÷ 1.2) + 1. Furring channels run along b, every 400 mm along a: rows = ceil(a ÷ 0.4) + 1. Hangers sit every 1.2 m on each main, first and last within 300 mm of the ends. One clip is counted at each main and furring crossing. The perimeter angle is 2 × (a + b).
- Partition, length L, height H. Studs = ceil(L ÷ spacing) + 1 at 600 mm (or 400 mm), plus two jamb studs for each door, each cut 20 mm shorter than the height. Track runs on the floor and under the slab, 2 × L.
- Stock pieces (3.0 or 3.6 m). A row longer than the stock length is counted as length × 1.10 ÷ stock length (10 percent for laps and splices). A row that fits inside one piece takes 1 ÷ whole rows per piece, because the off-cut is not usable: a 2.0 m furring row takes a whole 3.0 m piece, a 1.2 m row takes half of one. Pieces are rounded up once at the end. A stud taller than the stock length is counted as spliced pieces. This is why small bathrooms and corridors need more channel per metre than a large hall.
- Tall partitions. When the partition is higher than the board (for example 3.0 m high with 2.4 m boards) the boards are fixed in courses with a horizontal joint and the cut-offs are partly wasted. The calculator warns you: choose 2.7 or 3.0 m boards, or raise the waste to 15 to 20 percent.
- Screws: one every 200 mm along each furring channel, and one every 250 mm along each stud, for every face and layer, plus 5 percent. Boxes are 1,000 screws.
- Joint tape = visible face area × 1.25 m per m² (half the perimeter of a 1.2 × 2.4 m board ÷ its area) × 1.10, in rolls of 90 m. Joint compound = visible face area × 0.5 kg per m² (joints and screw heads, three passes), in 25 kg bags. Roll and bag sizes vary by supplier. Data sheets quote about 0.3 to 0.5 kg per m² for compound, so check yours.
- Mineral wool (optional) = net partition area × 1.05.
The door head track and the short studs above each door are not counted, and studs that fall inside a door opening are not deducted: the two roughly cancel out. Bulkheads, coves, access panels, light and AC cut-outs, beads and paint are not included. For paint use the paint calculator.
Worked example: majlis false ceiling 6 × 8 m
A single-layer ceiling of 8 × 6 m, 1.2 × 2.4 m boards, main channels every 1.2 m, furring every 400 mm, 3.0 m stock lengths and 10 percent board waste. These are the default inputs.
- Area 8 × 6 = 48 m². Boards 48 ÷ 2.88 = 16.67, so 17 boards. With 10 percent waste: 18.33, so 19 boards to order.
- Main channels: ceil((6 − 0.6) ÷ 1.2) + 1 = 6 rows of 8 m = 48 m. With 10 percent: 52.8 m ÷ 3 = 17.6, so 18 pieces. Hangers: ceil((8 − 0.6) ÷ 1.2) + 1 = 8 per main, 48 in total.
- Furring channels: ceil(8 ÷ 0.4) + 1 = 21 rows of 6 m = 126 m. With 10 percent: 138.6 m ÷ 3 = 46.2, so 47 pieces. Clips: 6 × 21 = 126.
- Perimeter angle: 2 × (8 + 6) = 28 m. With 10 percent: 30.8 ÷ 3 = 10.3, so 11 pieces.
- Screws: 126 ÷ 0.2 = 630, plus 5 percent = 661.5, so 662 (one box of 1,000).
- Tape: 48 × 1.25 × 1.10 = 66 m, so 1 roll of 90 m. Compound: 48 × 0.5 = 24 kg, so 1 bag of 25 kg.
The second example in the calculator, a 4.5 m × 3 m annex partition with one 0.9 × 2.1 m door lined on both faces, gives 9 boards, 11 studs, 4 pieces of track and 278 screws.
Notes for Dubai and the UAE
- Standard boards in the UAE are 1.2 m wide and 2.4 m long, with 3.0 m also available. Thickness, type (standard, moisture-resistant, fire-rated) and the framing system are set in the approved drawings and specification. Do not substitute a standard board where the drawing calls for moisture-resistant or fire-rated board.
- Use moisture-resistant boards in bathrooms, kitchens and utility rooms, and check the specification near AC drain points, because Dubai humidity and condensation can damage standard boards.
- Fire ratings of partitions and ceilings come from the project's fire strategy and the UAE Fire and Life Safety Code, enforced by Dubai Civil Defence. Fire-rated systems must be built as the tested system is, with the same board layers and fixings.
- Ceilings need access to AC units, valves and electrical junctions. Plan access panels and light and AC openings before the framing is set out. Heavy fittings are hung from the slab, not from the ceiling grid.
- Whether a villa interior change needs approval depends on what it changes. Ask your consultant or Dubai Municipality before altering structure, fire separation or services.
This tool counts materials only. For the cost of the whole annex, use the calculator in our app.
Frequently asked questions
How many gypsum boards do I need for a ceiling?
Divide the ceiling area by 2.88 m² for a 1.2 × 2.4 m board and add 10 percent for cutting. A 6 × 8 m majlis ceiling is 48 m², so 17 boards before waste and 19 to order.
How do I calculate a gypsum partition?
Multiply the length by the height, subtract the doors, and multiply by the number of faces and layers lined. Divide by the board area. The studs are one every 600 mm plus one at the end and two at each door, and the track runs on the floor and under the slab.
How many screws per board or per m²?
With channels every 400 mm and a screw every 200 mm, a ceiling takes about 13 screws per m². A partition with studs at 600 mm and a screw every 250 mm takes about 7 per m² of each face. The calculator counts from the actual framing and adds 5 percent.
How far apart should the channels be?
This calculator assumes main channels every 1.2 m and furring channels every 400 mm for 12.5 mm boards, and studs every 600 mm. The board and system data sheet sets the actual spacing, and closer spacing is used for thinner boards or heavy finishes.
Does it include paint, beads or lights?
No. It counts boards, framing, screws, tape and compound. Corner beads, bulkheads, access panels and cut-outs for lights and AC are extra. Paint has its own calculator.
Is the result exact?
It is a planning estimate from the sizes you enter and typical framing values. The approved drawings, the system supplier and your engineer always govern the final quantities.